SharePoint Document Issues

Synchronize a Project Online Plan with a SharePoint Task List

Jason MillerJason Miller Nov 20, 2026 869 views

Question details

The user wants to synchronize a Project Online plan with a SharePoint task list.

Synchronize a Project Online Plan with a SharePoint Task List
Product
Microsoft Project Online and SharePoint
Device & OS
not provided
Scenario
A project plan is managed in Project Online, and its tasks need to be available in a SharePoint list.
Observed behavior
Project Online does not directly publish the project as a SharePoint task list in Project Web App.
Before you start

Make sure you have access to the Project desktop client and an existing SharePoint site where you can create or edit a task list. Check that the project is connected to Project Online, saved to the Project Online database, and published if it is an enterprise project.

Solution 1Recommended

Sync a project plan from Project desktop to a SharePoint task list

Use the desktop client's SharePoint sync option when it is available for your project and site.

SharePoint task-list synchronization and Project Online publishing are different operations. The sync option may not be available for an enterprise project, and saving a separate copy to SharePoint does not automatically synchronize that copy with the Project Online database.

1
Open the plan

Open the project in the Microsoft Project desktop client. For a Project Online plan, connect to your Project Online account and open the project from there.

2
Select SharePoint sync

Go to File > Save As > Sync with SharePoint. If this option is unavailable for the open project, check your Project version and project type before proceeding.

3
Verify the site

Choose Existing SharePoint Site, enter the SharePoint site address, and select Verify Site.

4
Save to the task list

Enter a task-list name and select Save. Open the SharePoint site and check the task list to confirm that the tasks appear.

5
Check the enterprise project

If the plan is managed in Project Online, return to the enterprise project in Project desktop and confirm it is saved and published. Do not assume that changes to a separate SharePoint-synced copy update the enterprise project.

Sync a project plan from Project desktop to a SharePoint task list
Project sites are separate: Publishing an enterprise project can create an associated SharePoint Project Site if the Project Online administrator allows it. Creating that site does not by itself establish task-list synchronization.
Free Microsoft Office alternative

Review Project Task Data in WPS Spreadsheet

WPS Office is a free, lightweight alternative for reviewing task data in a familiar spreadsheet interface. Open compatible Excel files to work with exported project information; WPS does not establish Project Online-to-SharePoint synchronization.

Review and organize project task data in spreadsheets.Open and edit compatible Microsoft Excel XLSX and XLS files.Use a familiar interface to make the move from Microsoft Office easier.Work with a free, lightweight office suite.
microsoft office alternative - wps office

Frequently Asked Questions

Can Project Online directly publish a plan as a SharePoint task list?

Project Online publishing does not directly publish the plan as a SharePoint task list in Project Web App. When supported, use File > Save As > Sync with SharePoint in the Project desktop client.

What if Sync with SharePoint is unavailable?

Check the Project desktop version and the type of project you opened. The option may not be available for an enterprise project; a separate SharePoint-synced copy should not be assumed to update the Project Online database.

Does publishing a project create a SharePoint task list?

Publishing an enterprise project can create an associated SharePoint Project Site if the Project Online administrator permits site creation. The site is separate from task-list synchronization.

How can I check that synchronization worked?

After selecting Save in the SharePoint sync workflow, open the SharePoint site and locate the named task list. Check that the expected tasks appear.