Unlink a Subproject from a Microsoft Project Master File
Question details
Remove the link between an inserted subproject and a Microsoft Project master file without deleting the original project.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A master project contains a linked subproject that should no longer be linked to its source file.
- Observed behavior
- The subproject remains available as a separate file while its link to the master project is removed.
Open the master project and identify the summary line for the subproject you want to unlink. Make sure you can save changes to the master file.
Clear the subproject link in Microsoft Project
Use the inserted project settings to break the link while keeping the original subproject file.
In Microsoft Project, open the master file and locate the subproject summary line in a task view such as Gantt Chart.
Double-click a field on the subproject summary line to open the Inserted Project Information dialog box.
Clear the Link to project checkbox, then select OK.
Select Yes if prompted to save changes, and save the master project.
Use WPS Office for project documents and spreadsheets
WPS Office is a free, lightweight alternative for working with project reports and spreadsheets in a familiar interface. Its Microsoft Office format compatibility makes it easy to move supporting files between office suites. Unlinking a subproject still requires Microsoft Project.

Frequently Asked Questions
Does unlinking the subproject delete its original file?
No. Clearing Link to project in the Inserted Project Information dialog box removes the link; it does not delete the original subproject file.
Will the subproject tasks disappear from the master file?
Not necessarily. Clearing Link to project can leave the tasks in the master as an unlinked copy. Check the master task view after saving.
Will changes to the original subproject still appear in the master?
No. Once the link is cleared and the change is saved, the copy in the master no longer syncs with the original subproject.
Where can I find the Link to project option?
Open the master in Microsoft Project and double-click a field on the subproject summary line. The option is in the Inserted Project Information dialog box.