Preserve Subproject Formatting in a Microsoft Project Master File
Question details
The user wants to preserve custom subproject fonts, task colors, and Gantt bar styles in a Microsoft Project master file.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Multiple formatted subprojects are inserted into a master project and need to appear with the intended formatting.
- Observed behavior
- The master project uses its own view, so custom formatting from the subproject views does not automatically appear.
Open the master project and the subproject containing the formatting you want to reuse. Identify the custom view that contains the relevant text and Gantt bar styles.
Copy a Custom Subproject View to the Master Project
Use the Organizer to transfer a formatted view, then apply it in the master project.
Formatting is associated with a view. Copying the view makes its formatting available in the master project, but one applied view will not automatically reproduce separate views for different subprojects.
In the subproject, create a copy of the formatted Gantt Chart view and give it a distinctive name. If needed, use the Format tab to adjust Text Styles and Bar Styles in that view.
With both project files open, select File > Organizer. In some versions, the Organizer is available under File > Info.
On the Views tab, select the subproject as the source and the master project as the destination. Select the custom view and click Copy.
In the master project, open the View tab, choose More Views from the view list, select the copied view, and click Apply.
Use Format > Text Styles and Format > Bar Styles to make any additional changes needed for tasks from the other subprojects.

Build a Simple Project Schedule in WPS Spreadsheets
WPS Office is a free, lightweight alternative for creating spreadsheet-based project schedules with a familiar interface. It can help you move existing Office spreadsheets into a simple planning workflow, but it does not fix Microsoft Project master-view formatting.

Frequently Asked Questions
Why doesn't my subproject's Gantt formatting appear in the master project?
The master project displays tasks using its own view. Custom text and bar formatting stored in a subproject view is not automatically applied to that master view.
Can I apply a different view to each subproject in the same master task list?
No. A view applies to the displayed task list rather than to individual groups of tasks. Customize the master view's formatting rules or format relevant tasks manually if subprojects need different appearances.
Where can I copy a view between Microsoft Project files?
Open both files and select File > Organizer, or File > Info > Organizer in some versions. On the Views tab, choose the source and destination files, select the view, and click Copy.
How do I change Gantt bar and text styles in the master project?
Apply the desired view in the master project, then use the Format tab's Bar Styles and Text Styles commands to adjust its formatting.