How to Create a Custom Field for Task Contributions in Microsoft Project
Question details
The user needs a way to manually assign and track different task contributions to the overall project completion percentage.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Tracking custom project progress and manually setting task contribution weightings.
- Observed behavior
- Microsoft Project lacks a built-in field for manual task contribution weighting, requiring users to rely on custom number and formula fields for rollup calculations.
Ensure you have administrator or edit access to the project file and are familiar with customizing fields and formulas in Microsoft Project before making changes.
Track Task Contributions using Custom Number and Formula Fields
Use a custom Number field combined with a formula to track and roll up task completion percentages to the summary task.
By default, Microsoft Project calculates progress based on task duration. To track manual contribution values, you must create a dedicated custom number field for data entry and a secondary formula field to handle the rollup logic.
Navigate to the 'Project' tab on the ribbon and click on the 'Custom Fields' button in the Properties group.
Select 'Task' at the top of the dialog box, then choose 'Number' from the Type drop-down menu. Select an available field (e.g., Number1) and click 'Rename' to change its name to 'Contribution %'.
Select another empty Number field (e.g., Number2) and click the 'Formula' button. Enter a conditional formula to check completion, such as: IIf([% Complete]=100, [Number1], 0). Click 'OK' to save.
While still configuring the Number2 field, locate the 'Calculation for task and group summary rows' section. Select the 'Rollup' option and set the drop-down menu to 'Sum' so it calculates the total contribution for the summary task.

Use a Custom Flag to Identify Exceeded Allocations
Prevent tracking errors by setting up a flag field to visually warn you if the assigned percentages exceed the allowed total.
Track Project Progress Effectively with WPS Spreadsheet
If managing complex custom formulas in Microsoft Project becomes too cumbersome, consider using WPS Spreadsheet. It offers an intuitive, lightweight solution for project tracking, complete with free Gantt chart templates and full compatibility with Microsoft Excel formats.
- 1. Open WPS Spreadsheet: Launch WPS Office and select 'Spreadsheet' to create a new workbook.
- 2. Search for Project Templates: Click on 'New' and type 'Project' or 'Gantt' in the template search bar to explore pre-built layouts.
- 3. Manage Contributions Easily: Select a free template to effortlessly manage task allocations and completion percentages using standard spreadsheet formulas.

Frequently Asked Questions
Why doesn't Microsoft Project calculate task contribution automatically?
Microsoft Project primarily calculates overall project completion based on task duration rather than manual contribution weights. You must configure custom fields and formulas if you want to manually track specific weighting values.
Can I restrict users from entering more than 100% in the custom contribution field?
Native custom fields and formulas can only flag when a value exceeds 100%. To strictly prevent users from entering invalid data, you must write and apply a custom VBA macro in your project file.
How do I display these custom fields in my Gantt Chart view?
Right-click on the header of any existing column in your Gantt Chart view, select 'Insert Column', and type the name of your custom field (e.g., Number1 or Contribution %) to add it to the view.
Why isn't my summary task rolling up the contribution percentages?
Ensure that in the Custom Fields dialog box, under 'Calculation for task and group summary rows', the 'Rollup' option is selected and set to 'Sum'. Otherwise, the summary row will not aggregate the underlying custom field values.