Export a Microsoft Project Resource Allocation Report to Excel
Question details
Create an Excel report from a large Microsoft Project schedule, organized by resource and task with monthly work and allocation percentages.

- Product
- Microsoft Project and Microsoft Excel
- Device & OS
- not provided
- Scenario
- The user wants to analyze resource assignments and monthly allocation from a schedule containing about 5,000 tasks.
- Observed behavior
- The desired report shows each resource's tasks, monthly work, and percentage allocation in Excel.
Open the schedule in Microsoft Project and check that resource assignments and work estimates are up to date. Decide whether allocation should mean assigned work divided by each resource's available working hours for the month.
Create an Excel report with Microsoft Project Visual Reports
Use a built-in resource usage report to export time-phased project data and analyze it in an Excel PivotTable.
Available templates and PivotTable fields vary by Project version. Check whether the exported data includes the task detail and capacity needed for your report; a custom export may be required if it does not.
In Microsoft Project, open the schedule and select Report > Visual Reports. In some older versions, use Project > Reports > Visual Reports.
On the Excel tab in the Visual Reports dialog, choose a resource usage or resource work availability template. Set the usage data level to Months if that option is available, then select View.
In the generated Excel workbook, use the PivotTable Fields pane to arrange resources, tasks where available, and time periods in rows or columns. Add work and available-work fields to Values where provided.
For each resource and month, divide assigned work by available work in matching units. For example, enter =B2/C2 in an Excel cell and format it as a percentage; check for zero or missing capacity before calculating.
Select File > Save As in Excel and save the report as an XLSX workbook.

Copy monthly data from the Resource Usage view
Use this approach for a smaller selection or when you want to inspect resource and task assignments before transferring them to Excel.
Analyze exported resource reports in WPS Spreadsheet
After exporting the report from Microsoft Project, use free, lightweight WPS Spreadsheet to open and work with the Excel file. Its familiar spreadsheet interface and Excel format support make it easy to continue analysis without changing the export workflow.

Frequently Asked Questions
Where is Visual Reports in Microsoft Project?
In recent versions, select Report > Visual Reports. In some older versions, the path is Project > Reports > Visual Reports.
How do I calculate monthly resource allocation?
Divide the resource's assigned work for the month by their available work for the same month, using the same units for both. Format the result as a percentage in Excel.
Why doesn't my Visual Report show individual tasks?
The selected template or exported data may not include task-level fields. Check the PivotTable Fields pane and try a resource usage template; if the required detail is still unavailable, consider a custom VBA export.
What is the best approach for a 5,000-task schedule?
Start with a Visual Report to see whether its fields meet your needs. If you need a repeatable report with specific resource, task, and monthly columns, a custom VBA export may be more flexible than copying from Resource Usage.
Can WPS Spreadsheet export data directly from Microsoft Project?
Use Microsoft Project to generate or export the report first. You can then open the resulting XLSX workbook in WPS Spreadsheet to review and calculate the allocation data.