How to Vary Resource Allocation in a Microsoft Project Task

Phi Hung VoPhi Hung Vo Oct 1, 2026 868 views

Question details

The user needs to assign different daily work levels (hours) to a resource over the duration of a single task, rather than applying a single overall allocation percentage.

How to Vary Resource Allocation During a Microsoft Project Task
Product
Microsoft Project
Device & OS
Desktop
Scenario
Customizing the daily effort and work hours of a resource for a specific project task to reflect uneven workloads.
Observed behavior
Changing the allocation percentage for the latter part of a fixed-duration task automatically sets the first part of the task to 0%. The user is unable to easily contour the work using basic percentage edits.
Before you start

Ensure that your task is configured properly (e.g., avoid strict fixed-duration constraints if they interfere with workload recalculations). Using the timephased grid is the most accurate way to contour work.

Solution 1Recommended

Edit Timephased Work in the Task Usage View

The most reliable method to vary daily resource allocation is to switch to the Task Usage view and manually enter the specific work hours for each day.

By using the Task Usage view, you can bypass the limitations of overall allocation percentages. This allows you to create a "Manual" work contour, dictating exactly how many hours a resource works on specific days.

1
Open Task Usage View

Navigate to the 'View' tab on the main ribbon and select 'Task Usage' to display your project's tasks along with their assigned resources.

2
Display the Work Detail Row

On the right side of the screen in the timephased grid, right-click on the detail column. Ensure that 'Work' is checked so that the daily work hours row becomes visible.

3
Verify Initial Assignment

Make sure the resource is initially assigned to the task at a 100% allocation to establish the baseline workload.

4
Adjust Daily Work Hours

Click into the individual daily cells in the timephased grid. Type in the customized hours for each period (for example, enter 4 hours for the first 15 days, and leave 8 hours for the remaining days). Microsoft Project will automatically recalculate the total work based on your custom entries.

Edit Timephased Work in the Task Usage View
Automatic Recalculation: Once you manually enter the daily hours, Microsoft Project updates the total work automatically and changes the assignment contour type to 'Contoured'.
Free Microsoft Office alternative

Manage Projects Efficiently with WPS Office

While Microsoft Project is a specialized tool for complex tracking, everyday project management can easily be handled using spreadsheets. WPS Office offers a powerful, lightweight, and free alternative that lets you create Gantt charts and track resource allocation without the steep learning curve.

Completely free to use with a clean, intuitive, and familiar interface.Highly compatible with Microsoft Excel formats (.xlsx) for seamless project template sharing.Built-in project management templates, including Gantt charts and task trackers.Lightweight architecture ensures smooth performance on Windows, Mac, and mobile devices.
QA img-9

Frequently Asked Questions

Why does changing the percentage on a fixed-duration task set earlier days to 0%?

When you change the overall allocation percentage for the latter part of a fixed-duration task, Microsoft Project attempts to recalculate the remaining assignment, which can inadvertently zero out previous days. To avoid this, manually contour the daily hours in the timephased grid instead of changing the overall unit percentage.

How do I show the timephased Work grid if it is not visible?

In either the Task Usage or Resource Usage view, right-click anywhere on the right-hand grid (the timephased area) and select 'Work' from the context menu to display the row for daily work hours.

What does 'contouring' mean in Microsoft Project?

Contouring refers to the specific pattern of how work is distributed over the duration of a task assignment. By manually editing daily hours in the Task Usage view, you change the distribution from a 'Flat' contour (evenly distributed) to a 'Manual' contour.