Why Excel Paste Links to Microsoft Project Grouped Costs Return N/A
Question details
Understand why Excel cannot paste links to grouped cost summary lines in Microsoft Project and find another way to use the values.
- Product
- Microsoft Excel and Microsoft Project
- Device & OS
- not provided
- Scenario
- The user wants to link cost values from grouped summary lines in a Project Resource Usage view to Excel.
- Observed behavior
- Excel Paste Link returns N/A for grouped summary costs, although links to actual assignment lines can work.
In Project's Resource Usage view, identify whether the cost is on a grouping-generated summary line or an actual assignment line. Note the grouping criteria and cost field so you can reproduce the same total in Excel.
Calculate grouped costs from assignment data in Excel
Use assignment-level costs and the same grouping criteria to create totals that do not depend on links to display-only lines.
Grouping-generated summary lines in Project are display-only; they are not actual tasks or assignments and have no task ID. This is different from an actual summary task.
Include each relevant assignment once and use the same cost field and grouping criteria as the Project view.
In Project's Resource Usage view, select and copy the relevant assignment rows and fields, including the grouping field and Cost. Paste them into an Excel worksheet.
In Excel, enter a group label in E2. If column B contains group labels and column C contains assignment costs, enter =SUMIF(B2:B100,E2,C2:C100) in F2, adjusting the ranges to your data.
Compare the total in Excel with the grouped cost shown in Project. Check the included assignments and grouping criteria if the figures differ.
Copy a grouped cost or link to an actual assignment
Use a manually copied value for a one-time report, or link to an assignment line when a live link is needed and supported.
Calculate Project Cost Totals in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar spreadsheet interface. Open compatible Excel files and calculate grouped costs from assignment data with an easy transition from Microsoft Office. It does not fix Microsoft Project's Paste Link limitation.

Frequently Asked Questions
Why does Paste Link return N/A for a grouped cost?
A grouping-generated summary line in Project is display-only, not an actual task or assignment, and has no task ID. Excel cannot link to it like a real source record.
Can I link to an assignment cost instead?
Yes, links to actual assignment lines can work. Copy the assignment's Cost cell in Project, then in Excel choose Home > Paste > Paste Special > Paste Link and verify the result.
How can I reproduce a Project group total in Excel?
Copy the relevant assignment costs and grouping field into Excel, then use SUMIF to total costs for each group. Match Project's grouping criteria and include each relevant assignment once.
Will a copied grouped cost update automatically?
No. A value copied and pasted normally, or entered manually, is a snapshot. Copy or enter it again after the Project cost changes.