Why Excel WORKDAY Returns a Later Date Than Expected
Question details
The WORKDAY function calculates a date that is further out in the calendar than anticipated based on the number of days added.

- Product
- Microsoft Excel
- Device & OS
- not provided
- Scenario
- Calculating task deadlines or project timelines by adding a specific number of workdays to a starting date.
- Observed behavior
- The returned date is several calendar days later than the starting date despite only a few days being added, because the formula skips Saturdays and Sundays.
Verify your exact starting date and determine whether your task duration is meant to include or exclude standard weekend days.
Account for Standard Weekends in Your Calculation
Understand how the WORKDAY function automatically excludes Saturdays and Sundays to correctly interpret the returned date.
The WORKDAY function is specifically designed to calculate business days. It automatically skips weekends. For example, if your start date is a Wednesday (like May 5) and you add two workdays, the function counts Thursday and Friday, resulting in May 7. If you add three workdays, it skips Saturday and Sunday, returning Monday, May 10.
Because of this, calendar dates will jump significantly when calculations cross over a weekend.
Click on the cell containing your initial date and confirm it is the exact day you intend to start counting from.
Ensure the number of days you are adding in the formula represents business days, not total calendar days.
If your project actually requires counting weekends (standard calendar days), replace the WORKDAY formula with a simple addition formula, such as '=Start_Date + Days'.

Include a Holiday Range to Refine Your Results
Prevent the WORKDAY function from counting recognized public holidays as business days by specifying a holiday range.
Accurately Calculate Deadlines with WPS Spreadsheet
WPS Spreadsheet fully supports both the WORKDAY and WORKDAY.INTL functions, making it incredibly simple to calculate business days, project timelines, and delivery dates. It offers a seamless experience with complete formula compatibility.
- 1. Open your schedule: Launch WPS Spreadsheet and open the document containing your project timeline or date data.
- 2. Insert the function: Select an empty cell where you want the deadline to appear, type '=WORKDAY(', and select your starting date cell.
- 3. Input the duration: Type a comma, enter the number of business days to add, and optionally select your holiday date range.
- 4. Execute the calculation: Close the parenthesis and press Enter to instantly see the calculated business day.

Frequently Asked Questions
Can I use the WORKDAY function if my only day off is Sunday?
Yes, but you will need to use the WORKDAY.INTL function instead of WORKDAY. The WORKDAY.INTL function allows you to specify custom weekend parameters, such as setting only Sunday as the non-working day using a weekend code (like 11).
Does the WORKDAY function count the start date as day one?
No, the WORKDAY function starts counting from the day immediately following the start date. If your task begins on the start date and you want that day included in the total duration, you should subtract 1 from your days argument.
Why is my WORKDAY formula returning a #VALUE! error?
A #VALUE! error typically occurs if the start date or any of the holiday dates are not recognized as valid date formats by the spreadsheet, or if the days argument is non-numeric. Ensure all referenced cells are formatted properly as Dates or Numbers.
How do I calculate the number of workdays between two known dates?
To find the number of business days between two specific dates, you should use the NETWORKDAYS function rather than WORKDAY. NETWORKDAYS calculates the total duration, whereas WORKDAY calculates the end date based on a given duration.