Add Default Tasks to New Projects in Project Web App
Question details
Set up standard tasks so they appear automatically in new Project Web App projects.

- Product
- Microsoft Project Web App and Project Online
- Device & OS
- not provided
- Scenario
- An organization wants new projects created through selected enterprise project types to start with a consistent task structure.
- Observed behavior
- New projects should include predefined tasks, durations, and project structure from a project template.
Identify the standard tasks and the enterprise project types that should use them. Confirm that you can edit project templates in Project desktop and have the permissions needed to configure enterprise project types in Project Web App.
Assign a project template to an enterprise project type
Use this approach to include the same starting tasks in projects created with a specific enterprise project type.
A project template defines the project plan, including tasks and durations. A project site template controls the associated site's layout and content, not the project's task schedule.
In Project desktop, create or open a project and enter the standard tasks, durations, dependencies, and structure you want new projects to inherit.
Select File > Save As and save the plan as a project template. Make the template available to your Project Web App environment according to your organization's configuration.
In Project Web App, open Settings > PWA Settings > Enterprise Project Types. Edit the relevant project type, select the project plan template, and save the changes. Repeat for other project types that need the same tasks.
In Project Web App, create a project using the configured enterprise project type. Check that the expected tasks, durations, and dependencies appear, then publish the project.

Create a project from a template in Project desktop
Use this option when you want to start a project from a template manually and then publish it to Project Web App.
Plan standard project tasks with WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface and Microsoft Office format compatibility. Use WPS Spreadsheets to maintain a reusable task list and move existing spreadsheet plans over easily. It does not configure Project Web App templates or enterprise project types.

Frequently Asked Questions
Should I use a project template or a project site template for default tasks?
Use a project template for tasks, durations, and the project schedule. A project site template is for the associated site's layout and content.
Where do I assign the template to a project type?
In Project Web App, go to Settings > PWA Settings > Enterprise Project Types, edit the relevant type, and select its project plan template. You may need administrator permissions.
Will changing the template update projects that already exist?
No. Template changes apply when you create projects from the updated template; existing projects must be changed separately.
What risks should I check before using a standard template?
Review task dates, dependencies, durations, and any assignments in Project desktop before saving the template. Create a test project through the intended enterprise project type to make sure the inherited schedule is appropriate.
Why don't the default tasks appear in a new project?
Check that the project was created with the intended enterprise project type and that its project plan template is selected under PWA Settings > Enterprise Project Types. Also confirm that the template is available to your Project Web App environment.