Question details

The user needs to make planned or future tasks available for time reporting in a Project Web App timesheet.

How to Add Future Tasks to a Project Web App Timesheet
Product
Project Web App
Device & OS
not provided
Scenario
Reporting time on project tasks that are scheduled for the future but require early progress recording.
Observed behavior
Future tasks do not automatically appear on the Timesheet page, which normally only displays current tasks and past tasks requiring progress.
Before you start

Before adding future tasks, verify with your project manager that early reporting is permitted, as this can affect project tracking metrics and schedule dates.

Solution 1Recommended

Manually Adding Tasks from Existing Assignments

Use the Add Row feature on the Timesheet ribbon to pull future assignments into your current timesheet view.

By design, future tasks do not automatically populate on the Timesheet page. You must manually fetch them from your existing project assignments.

Be cautious when doing this: reporting time on a future task creates early or out-of-sequence progress. It should be used sparingly to avoid distorting the actual project timeline.

1
Access your Timesheet

Log in to Project Web App and navigate to your active Timesheet page.

2
Click Add Row

Look at the Timesheet ribbon located at the top of the page and click on the 'Add Row' button.

3
Select from Existing Assignments

From the dropdown options, choose 'Select from Existing Assignments'. Locate the specific future task you want to work on and add it to your current timesheet view.

Manually Adding Tasks from Existing Assignments
Review Project Schedules: If you frequently find yourself needing to add future tasks to your current timesheet, it likely indicates that your project schedule dates do not reflect actual work patterns. It is highly recommended to review and adjust the task dates accordingly.
Free Microsoft Office alternative

Manage Project Schedules and Timesheets with WPS Office

While Project Web App is designed for complex enterprise management, WPS Office provides a free, lightweight alternative for handling tasks, schedules, and timesheets using robust spreadsheet and document tools. It offers complete format compatibility and seamless migration for your daily project data.

  1. 1. Download and Install: Visit the WPS Office website to download the free suite to your computer or mobile device.
  2. 2. Open a Spreadsheet: Launch WPS Spreadsheets to easily create a new project tracker, task list, or timesheet.
  3. 3. Apply a Template: Search the built-in template library for 'Timesheet' or 'Project Schedule' to quickly set up your task tracking without starting from scratch.
Fully compatible with Microsoft Excel (.xlsx) formats for custom timesheet templates.Lightweight and fast, ideal for managing and sharing project schedules on any device.Free to use with a familiar, intuitive user interface that requires zero learning curve.Includes a rich library of built-in templates for project planning and time tracking.
microsoft office alternative - wps office

Frequently Asked Questions

Why don't future tasks show up automatically in my PWA timesheet?

By default, the Timesheet page is designed to display only current tasks and past tasks that still require progress updates. This keeps the view clean and strictly relevant to the active reporting period.

What happens when I record progress on a future task?

Recording progress on a task scheduled for the future creates out-of-sequence or early progress. This can skew the project's critical path and schedule variances, which is why project managers advise doing it sparingly.

Can I remove a future task I accidentally added to my timesheet?

Yes, you can typically delete a manually added row from your timesheet before submitting it, provided no actual time has been saved against that specific task for the current period.