Question details

The user needs to record a resource's planned PTO so it can be accounted for in a Project Online schedule.

Add Resource PTO to a Microsoft Project Online Schedule
Product
Microsoft Project Online
Device & OS
not provided
Scenario
A project manager needs to add planned leave as nonworking time for an enterprise resource.
Observed behavior
The project manager may be unable to edit the resource calendar because the required permissions are restricted to administrators.
Before you start

Confirm the resource name, PTO dates and any partial-day hours. Check whether your organization uses Project Web App (PWA) timesheets and who administers enterprise resource calendars.

Solution 1Recommended

Ask an administrator to add PTO to the resource calendar

Use this approach when you cannot edit the enterprise resource calendar yourself.

1
Send the leave details

Contact your Project Server or Project Online administrator with the resource name, PTO dates, time zone and any partial-day hours.

2
Request a calendar exception

Ask the administrator to open the resource's enterprise calendar and add the dates as a nonworking exception, using the calendar editing tools available to them.

3
Check the schedule

After the administrator saves the change, open the project schedule in Project Online or Project Professional and check the resource's assignments for the affected dates.

Ask an administrator to add PTO to the resource calendar
Calendar permissions: The administrator may need to use Project Professional and have the appropriate enterprise resource editing permissions. Schedule changes also depend on task settings and scheduling constraints.
Free Microsoft Office alternative

Track PTO details in WPS Office

WPS Office is a free, lightweight alternative for preparing leave lists and project status documents. Its familiar interface and Microsoft Office format support make it easy to move everyday files between office suites. It does not change Project Online resource calendars.

Keep resource names and planned PTO dates together in a spreadsheetOpen and edit Microsoft Excel XLSX and Word DOCX filesUse a familiar interface for everyday documents and spreadsheetsShare office files with colleagues while continuing to manage scheduling in Project Online
microsoft office alternative - wps office

Frequently Asked Questions

Why can't I add PTO to a resource calendar?

Editing an enterprise resource calendar may require permissions reserved for a Project Online or Project Server administrator. Contact your administrator and provide the resource name and leave dates.

Will entering PTO in a PWA timesheet update the project schedule?

Not necessarily. Timesheet behavior depends on your organization's configuration, and a timesheet entry should not be assumed to change the resource calendar. Ask your administrator whether a calendar exception is also needed.

How do I record a half-day of PTO?

Give the administrator the date and exact nonworking hours so they can create an appropriate resource calendar exception. If your organization uses timesheets, enter the corresponding hours in its PTO category as well.

Can WPS Office edit a Project Online resource calendar?

No. Use Project Online or the administrator's Project tools to manage the resource calendar. WPS Spreadsheets can help you maintain a separate PTO list in an Excel-compatible file.