Add Resource Vacation Time in Project Online and PWA
Question details
Record vacation, PTO, and other non-working time for enterprise resources.

- Product
- Microsoft Project Online and Project Web App
- Device & OS
- not provided
- Scenario
- A resource manager wants planned absences reflected in enterprise resource calendars for project scheduling.
- Observed behavior
- Each resource's calendar should show the selected dates as non-working time.
Make sure you have permission to edit enterprise resources and access to a compatible Microsoft Project desktop client connected to your Project Online account. Identify the resources and their planned absence dates.
Add PTO to enterprise resource calendars through PWA
Use Resource Center and Microsoft Project to record non-working dates for each enterprise resource.
In Project Web App (PWA), open Resource Center and select the enterprise resources whose calendars need updating.
Use the Resource Center option to open the selected resources in Microsoft Project. Sign in to the connected Project Online account if prompted.
In Microsoft Project, double-click a resource to open Resource Information, then select Change Working Time.
Select the vacation dates in the calendar grid. On the Exceptions tab, enter a name such as Vacation or PTO and confirm the start and finish dates, then select OK.
Repeat the calendar edit for each selected resource. Save the changes in Microsoft Project, then close the resource editing session and check the resources back in if prompted.

Track planned PTO in WPS Spreadsheets
WPS Office is a free, lightweight alternative for maintaining a separate PTO tracker. Its familiar interface and Microsoft Office format support make it easy to move existing spreadsheets, but it does not update Project Online enterprise calendars.

Frequently Asked Questions
Where do I enter an enterprise resource's vacation dates?
In PWA Resource Center, open the resource for editing in Microsoft Project. Double-click the resource, select Change Working Time, and add the dates on the Exceptions tab.
Do I need to create a separate calendar for each resource?
No. Each enterprise resource already has an individual enterprise calendar. Add vacation or PTO as an exception to that resource's calendar.
What should I do if I cannot edit a resource calendar?
Ask your Project Online administrator to check your resource editing permissions and whether the resource is checked out by someone else. Also verify that Microsoft Project is connected to the correct Project Online account.
Can a WPS spreadsheet update the Project Online resource calendar?
No. WPS Spreadsheets can maintain a separate PTO tracker, but you must enter calendar exceptions through PWA and Microsoft Project to update enterprise resource availability.