Add Resource Vacation Time in Project Online and PWA

Bushra ParveenBushra Parveen Nov 20, 2026 868 views

Question details

Record vacation, PTO, and other non-working time for enterprise resources.

Add Resource Vacation Time in Project Online and PWA
Product
Microsoft Project Online and Project Web App
Device & OS
not provided
Scenario
A resource manager wants planned absences reflected in enterprise resource calendars for project scheduling.
Observed behavior
Each resource's calendar should show the selected dates as non-working time.
Before you start

Make sure you have permission to edit enterprise resources and access to a compatible Microsoft Project desktop client connected to your Project Online account. Identify the resources and their planned absence dates.

Solution 1Recommended

Add PTO to enterprise resource calendars through PWA

Use Resource Center and Microsoft Project to record non-working dates for each enterprise resource.

1
Open Resource Center

In Project Web App (PWA), open Resource Center and select the enterprise resources whose calendars need updating.

2
Open the resources for editing

Use the Resource Center option to open the selected resources in Microsoft Project. Sign in to the connected Project Online account if prompted.

3
Open a resource calendar

In Microsoft Project, double-click a resource to open Resource Information, then select Change Working Time.

4
Enter the absence dates

Select the vacation dates in the calendar grid. On the Exceptions tab, enter a name such as Vacation or PTO and confirm the start and finish dates, then select OK.

5
Save and check in

Repeat the calendar edit for each selected resource. Save the changes in Microsoft Project, then close the resource editing session and check the resources back in if prompted.

Add PTO to enterprise resource calendars through PWA
Check permissions: If you cannot open or edit a resource, ask your Project Online administrator to check your permissions and whether the resource is already checked out.
Free Microsoft Office alternative

Track planned PTO in WPS Spreadsheets

WPS Office is a free, lightweight alternative for maintaining a separate PTO tracker. Its familiar interface and Microsoft Office format support make it easy to move existing spreadsheets, but it does not update Project Online enterprise calendars.

Create a separate spreadsheet to track resource vacation and PTO datesOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface for an easier transitionWork with a lightweight office suite available for free
microsoft office alternative - wps office

Frequently Asked Questions

Where do I enter an enterprise resource's vacation dates?

In PWA Resource Center, open the resource for editing in Microsoft Project. Double-click the resource, select Change Working Time, and add the dates on the Exceptions tab.

Do I need to create a separate calendar for each resource?

No. Each enterprise resource already has an individual enterprise calendar. Add vacation or PTO as an exception to that resource's calendar.

What should I do if I cannot edit a resource calendar?

Ask your Project Online administrator to check your resource editing permissions and whether the resource is checked out by someone else. Also verify that Microsoft Project is connected to the correct Project Online account.

Can a WPS spreadsheet update the Project Online resource calendar?

No. WPS Spreadsheets can maintain a separate PTO tracker, but you must enter calendar exceptions through PWA and Microsoft Project to update enterprise resource availability.