The user needs to increase or decrease the height of task rows in Microsoft Project 2016 Gantt Chart view.

Change Task Row Height in Microsoft Project 2016 Gantt Chart
Product
Microsoft Project 2016
Device & OS
not provided
Scenario
Adjust the Gantt Chart layout to give task information more vertical space or display more tasks on screen.
Observed behavior
The desired result is a Gantt Chart with task rows displayed at the selected height.
Before you start

Open your project in Gantt Chart view and check which table is displayed. The instructions below use the Entry table; if you use a different table, select that table instead.

Solution 1Recommended

Adjust Gantt Chart Row Height Through the Entry Table Settings

Use the table's Row height setting to apply a consistent height to task rows in Gantt Chart view.

1
Open the table selection dialog

In Microsoft Project 2016, open the View tab, select Tables, and choose More Tables.

2
Edit the Entry table

In the More Tables dialog, select Entry and click Edit. If your Gantt Chart uses another table, select that table instead.

3
Set the row height

Near the bottom of the table editing dialog, locate Row height and enter the required value. Increase the value for taller rows or reduce it for shorter rows.

4
Apply the updated layout

Click OK to save the table settings, then click Apply in the More Tables dialog to display the updated row height.

Adjust Gantt Chart Row Height Through the Entry Table Settings
Choose the table used by your view: Row height is a table setting. Edit and apply the table you want to display in the Gantt Chart, rather than changing an unrelated table.
Free Microsoft Office alternative

Use WPS Office for Spreadsheet-Based Task Planning

WPS Office is a free, lightweight, easy-to-use alternative for everyday Office work. Its familiar interface and Microsoft Office format compatibility make migration straightforward. Use WPS Spreadsheet to organize task lists and adjust spreadsheet row heights; it does not change Microsoft Project 2016 Gantt Chart settings or replace Project's scheduling features.

Organize task names, dates, owners, and progress in a spreadsheet with adjustable row heights.Work with Microsoft Excel .xlsx and .xls files for spreadsheet-based planning.Use a familiar Office-style interface to move existing spreadsheet workflows into WPS.Access document, spreadsheet, and presentation tools in one lightweight application.
microsoft office alternative - wps office

Frequently Asked Questions

Where is the Row height setting in Microsoft Project 2016?

Go to View > Tables > More Tables, select the table used by your Gantt Chart, and click Edit. The Row height setting is near the bottom of the table editing dialog.

Can I make task rows shorter as well as taller?

Yes. Open the table's Edit dialog and reduce the Row height value for shorter rows or increase it for taller rows. Click OK, then Apply to update the view.

What if my Gantt Chart uses a table other than Entry?

Go to View > Tables > More Tables and select the table you actually use. Click Edit, change Row height, then click OK and Apply. Editing Entry will not update the settings of a different table.

Can WPS Office change row height in a Microsoft Project Gantt Chart?

No. Change Microsoft Project Gantt Chart row height inside Project using View > Tables > More Tables > Edit. WPS Spreadsheet can adjust rows in spreadsheet-based task lists, but it does not modify Project's Gantt Chart settings.