Compare Expected and Actual Project Progress in Microsoft Project

Maira MehtabMaira Mehtab Nov 14, 2026 868 views

Question details

Compare the progress expected by a status date with the project's actual progress.

Compare Expected and Actual Project Progress in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A project manager wants to assess progress at a particular status date.
Observed behavior
The goal is to view or calculate an expected completion percentage and compare it with actual completion using a consistent measure.
Before you start

Enter the latest actual progress and note the current Project Summary Task percentage before calculating a projection. Check whether you need a projection based on the current schedule or a comparison against a saved baseline; these are different measures.

Solution 1Recommended

Estimate Progress Through a Status Date in a Copy of the Project

Use a temporary project copy to estimate how much of the current schedule would be complete by the chosen date.

This method updates task progress in the copy. It produces a schedule-based estimate, not necessarily the percentage originally planned in the baseline.

1
Record actual completion

On the Format tab, turn on Project Summary Task. Note its current % Complete value; add the % Complete column if it is not visible.

2
Create a working copy

Select File > Save As and save a separate copy for the calculation so the temporary updates do not change the original project.

3
Set the status date

In the copy, select Project > Status Date and enter the date you want to assess.

4
Update scheduled work

Select Project > Update Project. Choose Update work as complete through, enter the same date, select Entire project, and confirm.

5
Compare the percentages

Read the updated % Complete value on the Project Summary Task and compare it with the actual value recorded earlier. Close the working copy when finished.

Estimate Progress Through a Status Date in a Copy of the Project
Interpret the estimate carefully: The update uses the current schedule and existing progress. Changes to dates or progress can make the result different from the original baseline plan.
Free Microsoft Office alternative

Track Project Progress in WPS Spreadsheets

WPS Office is a free, lightweight alternative for working with project tracking spreadsheets. Its familiar interface and Excel format support make it easy to move spreadsheet data into WPS, although it does not replace Microsoft Project's scheduling features.

Calculate planned and actual work percentages with spreadsheet formulasOpen and save Microsoft Excel XLSX filesUse a familiar spreadsheet interface for project trackingMove spreadsheet data into a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see the overall project completion percentage?

On the Format tab, turn on Project Summary Task, then review its % Complete field. Add the column if it is not visible.

Does Update Project show the original baseline progress?

Not necessarily. Project > Update Project updates progress using the current schedule and existing task information. Use saved baseline data for a comparison with the original plan.

Will updating work through a date change my project?

Yes. Update work as complete through changes task progress. Run the calculation in a separate copy created with File > Save As if you only need an estimate.

Can I compare baseline work percentages with % Complete?

Not directly. Baseline work calculations measure effort, while % Complete is duration-based. Compare percentages calculated using the same measure and denominator.