Use Baseline 1 or Baseline 2 for Progress Lines in Microsoft Project 2016

Kushani NimanthikaKushani Nimanthika Nov 22, 2026 868 views

Question details

The user wants to reference Baseline 1 or Baseline 2 in Progress Lines while preserving the original baseline.

Use Baseline 1 or Baseline 2 for Progress Lines in Microsoft Project 2016
Product
Microsoft Project 2016
Device & OS
not provided
Scenario
A project has multiple saved baselines, and the user wants to compare progress against a specific additional baseline.
Observed behavior
Progress Lines offers Actual Plan and Baseline Plan references, but no direct option to select Baseline 1 or Baseline 2.
Before you start

Open the project in Microsoft Project 2016 and confirm that Baseline 1 or Baseline 2 has already been saved. Use a Gantt Chart view to access Progress Lines and inspect baseline fields.

Solution 1Recommended

Check the available Progress Lines references

Use this method to confirm which references Progress Lines supports in Project 2016.

1
Open the Gantt Chart

Open your project and select View > Gantt Chart.

2
Open Progress Lines

Select Format > Gridlines > Progress Lines.

3
Review the reference choices

In the Progress Lines settings, review the Actual Plan and Baseline Plan choices. There is no direct selector for Baseline 1 or Baseline 2.

Check the available Progress Lines references
Additional baselines: Choosing Baseline Plan does not provide a way to select Baseline 1 or Baseline 2. Use baseline fields to compare those saved plans without replacing the original baseline.
Free Microsoft Office alternative

Review exported project data in WPS Spreadsheets

WPS Office is a free, lightweight, easy-to-use alternative with a familiar interface for reviewing project data exported to a spreadsheet. It does not change Microsoft Project's Progress Lines or replace its baseline features.

Compare exported project dates in a familiar spreadsheet interfaceCompatible with Microsoft Excel XLS and XLSX filesSupports Word DOCX and PowerPoint PPTX files for easier migrationFree and lightweight for everyday office work
QA img-9

Frequently Asked Questions

Can I select Baseline 1 directly for a Progress Line?

No. In Project 2016, Format > Gridlines > Progress Lines offers Actual Plan and Baseline Plan, but no direct Baseline 1 or Baseline 2 selector.

How can I see Baseline 2 dates alongside current dates?

In View > Gantt Chart, right-click a column heading and select Insert Column. Add Baseline2 Start and Baseline2 Finish, then compare them with the Start and Finish columns.

Will adding baseline columns overwrite the original baseline?

No. Insert Column displays saved field values; it does not save or replace a baseline.

Can WPS Office make Microsoft Project use Baseline 1 for Progress Lines?

No. WPS Office cannot change Microsoft Project's Progress Lines settings. You can use WPS Spreadsheets to review project data exported to a compatible Excel file.