Use Baseline 1 or Baseline 2 for Progress Lines in Microsoft Project 2016
Question details
The user wants to reference Baseline 1 or Baseline 2 in Progress Lines while preserving the original baseline.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- A project has multiple saved baselines, and the user wants to compare progress against a specific additional baseline.
- Observed behavior
- Progress Lines offers Actual Plan and Baseline Plan references, but no direct option to select Baseline 1 or Baseline 2.
Open the project in Microsoft Project 2016 and confirm that Baseline 1 or Baseline 2 has already been saved. Use a Gantt Chart view to access Progress Lines and inspect baseline fields.
Check the available Progress Lines references
Use this method to confirm which references Progress Lines supports in Project 2016.
Open your project and select View > Gantt Chart.
Select Format > Gridlines > Progress Lines.
In the Progress Lines settings, review the Actual Plan and Baseline Plan choices. There is no direct selector for Baseline 1 or Baseline 2.

Compare Baseline 1 or Baseline 2 using task columns
Use this alternative when you need to inspect dates from an additional baseline while keeping the original baseline intact.
Review exported project data in WPS Spreadsheets
WPS Office is a free, lightweight, easy-to-use alternative with a familiar interface for reviewing project data exported to a spreadsheet. It does not change Microsoft Project's Progress Lines or replace its baseline features.

Frequently Asked Questions
Can I select Baseline 1 directly for a Progress Line?
No. In Project 2016, Format > Gridlines > Progress Lines offers Actual Plan and Baseline Plan, but no direct Baseline 1 or Baseline 2 selector.
How can I see Baseline 2 dates alongside current dates?
In View > Gantt Chart, right-click a column heading and select Insert Column. Add Baseline2 Start and Baseline2 Finish, then compare them with the Start and Finish columns.
Will adding baseline columns overwrite the original baseline?
No. Insert Column displays saved field values; it does not save or replace a baseline.
Can WPS Office make Microsoft Project use Baseline 1 for Progress Lines?
No. WPS Office cannot change Microsoft Project's Progress Lines settings. You can use WPS Spreadsheets to review project data exported to a compatible Excel file.