Control Resource Leveling Priority in Microsoft Project 2010

Phi Hung VoPhi Hung Vo Nov 22, 2026 868 views

Question details

The user wants to understand and control the order in which Microsoft Project 2010 levels tasks competing for the same resource.

Control Resource Leveling Priority in Microsoft Project 2010
Product
Microsoft Project 2010
Device & OS
not provided
Scenario
Multiple tasks share an overallocated resource and have identical default priority values.
Observed behavior
Project may choose an unexpected leveling order because several valid schedules are possible and factors such as slack, task relationships, and constraints influence the result.
Before you start

Identify the tasks competing for the resource and review their dependencies, constraints, and slack. Check the current leveling order in Resource > Leveling Options before changing task priorities.

Solution 1Recommended

Set Task Priorities and Use Priority-Based Leveling

Use this method to tell Project which tasks should generally be protected from leveling delays.

Project can select among several valid schedules when tasks compete for a resource. Higher priority values generally make tasks less likely to be delayed; the default priority is 500.

1
Open task information

In the Gantt Chart view, double-click a task that competes for the overallocated resource to open Task Information.

2
Set the priority

On the General tab, set Priority to a meaningful value from 0 to 1000. For example, leave a normal task at 500 and give a more important task 600, then click OK.

3
Choose the leveling order

Go to Resource > Leveling Options and select Priority, Standard under Leveling order. Click OK.

4
Level and review the schedule

On the Resource tab, select Level All, then review the affected task dates and resource allocations in the Gantt Chart.

Set Task Priorities and Use Priority-Based Leveling
Priority guides the result: Dependencies, constraints, and other scheduling settings still affect the outcome. A priority of 1000 prevents Project from leveling that task.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheets

WPS Office is a free, lightweight alternative for maintaining task lists and sharing project reports. Its familiar interface and Microsoft Office format compatibility make it easy to move existing documents and spreadsheets. It does not replace Microsoft Project's resource-leveling engine.

Organize task priorities, owners, and dates in a spreadsheetOpen and save Microsoft Excel XLSX files and work with Word DOCX documentsUse a familiar interface to move existing Office work into WPSCreate and edit documents with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does Project level tasks with the same priority in a different order than I expected?

Identical priorities do not guarantee a particular order. Depending on the leveling settings, Project can consider factors such as task relationships, slack, dates, and constraints when selecting a valid schedule.

What is the default task priority in Project 2010?

The default is 500. Double-click a task in the Gantt Chart and check Priority on the General tab of Task Information.

How do I stop Project from leveling a particular task?

Open the task's Task Information dialog, select the General tab, and set Priority to 1000. Project will not level that task.

Should I use ID Only or Priority, Standard for leveling?

Choose Priority, Standard in Resource > Leveling Options when task importance should guide the result. Choose ID Only when you want leveling to follow task ID order instead.