Why Microsoft Project Changes Task Dates in Manual Leveling Mode
Question details
Understand why assigning a resource changes a task's finish date when resource leveling is set to Manual.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- An auto-scheduled task is assigned a resource whose calendar allows four working hours per day, while Project Options specifies eight hours per day.
- Observed behavior
- The task finish date extends after the resource is assigned, even though resource leveling is set to Manual.
Identify the affected task and assigned resource, and note the task's work, duration, and finish date. Check whether the resource is intended to work four or eight hours per day before changing its calendar.
Check the Resource Calendar and Task Scheduling Settings
Use this approach to find why Project recalculates the task and align the settings with the intended working schedule.
Manual leveling prevents Project from automatically leveling resource overallocations; it does not prevent normal scheduling calculations. For example, eight hours of work assigned to a resource available for four hours per day can require two working days.
The Hours per day setting controls how Project converts entered durations and work units; it does not set a resource's actual working hours. Working time comes from the applicable calendars.
Open the Resource tab, select Leveling Options, and check that leveling calculations are set to Manual.
Open Project > Change Working Time, select the resource in the calendar list, and review its working hours and exceptions. Change them only if they do not reflect the resource's actual availability.
Open File > Options > Schedule and review Hours per day and other calendar options. Set them to match the intended interpretation of durations, while keeping in mind that this does not change calendar working hours.
Select the task and open Task > Information. Check whether it is auto-scheduled, then review the task type and effort-driven setting on the Advanced tab. Choose settings appropriate for how work, duration, and assignment units should respond to changes.
Open View > Resource Sheet and look for red resource indicators. Investigate any overallocated resources without running a leveling command unless you intend Project to resolve the conflicts.

Review Exported Project Data in WPS Spreadsheets
WPS Office is a free, lightweight alternative for reviewing project data in a familiar spreadsheet interface. Export data from Microsoft Project to an Excel file to make it easier to share and work with in WPS; WPS does not fix Microsoft Project's scheduling calculations.

Frequently Asked Questions
Does manual leveling prevent all task date changes?
No. Manual leveling stops automatic resource leveling, but auto-scheduled tasks can still be recalculated when assignments, calendars, or other scheduling inputs change.
Why does a four-hour resource calendar extend a task?
A resource available for four hours per day may need more working days to complete the assigned work. Check the resource's hours under Project > Change Working Time and compare them with the task's work and assignment units.
Does changing Hours per day change the resource calendar?
No. File > Options > Schedule controls time-unit conversions, while Project > Change Working Time controls calendar working hours.
How can I check for overallocated resources without leveling?
Open View > Resource Sheet and look for red indicators. Keep Resource > Leveling Options set to Manual and avoid running a leveling command until you want Project to resolve the overallocations.