How to Use Microsoft Project Resource Leveling for Automatic Scheduling
Question details
The user wants to know how to adjust a project schedule automatically when additional resources become available, without artificially linking independent tasks.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Resolving resource over-allocation and scheduling independent tasks when managing a project schedule.
- Observed behavior
- Users often incorrectly link independent tasks to avoid resource over-allocation, rather than utilizing the software's built-in automatic resource leveling features.
Ensure you have added all necessary resources to your project file and assigned them to their respective tasks with accurate durations.
Apply Resource Leveling to Resolve Over-allocation
Use the built-in leveling feature to automatically adjust task schedules based on resource availability instead of linking unrelated tasks.
Resource leveling is the standard method for solving resource conflicts in Microsoft Project. By applying leveling, the software automatically shifts task dates to accommodate resource limits while keeping independent tasks unlinked.
Create your project tasks (e.g., Task A, Task B, Task C) and enter their actual work durations.
Leave the independent tasks unlinked and assign the appropriate resources. Do not worry if they initially appear over-allocated.
On the main application ribbon, click on the 'Resource' tab to access resource management tools.
Click on 'Leveling Options' in the Level group to open the resource leveling dialog box.
Clear the initial leveling options if necessary, apply your desired settings, and test the scheduling results to see the automatic adjustments.
Manage Your Projects Efficiently with WPS Office
While Microsoft Project is dedicated to complex project management, WPS Office provides a free, lightweight, and highly compatible alternative for everyday project tracking. You can easily manage timelines, resource allocation, and task tracking using pre-built Gantt chart templates in WPS Spreadsheet.
- 1. Download and Install: Download WPS Office for free from the official website and install it on your device.
- 2. Open WPS Spreadsheet: Launch WPS Office and open a new Spreadsheet document.
- 3. Use a Project Template: Click on 'Templates' and search for 'Project Management' or 'Gantt Chart' to instantly start tracking your schedule and resources.

Frequently Asked Questions
What is resource leveling in Microsoft Project?
Resource leveling is a scheduling tool in Microsoft Project that resolves resource over-allocation by delaying tasks or splitting them until the assigned resources are available, without altering actual task durations.
Why shouldn't I link independent tasks to fix over-allocation?
Linking tasks creates a false dependency in your project schedule. If one task changes, it artificially forces the other to move, which reduces schedule flexibility and distorts project reporting.
Where can I find the Leveling Options in Microsoft Project?
You can access Leveling Options by clicking on the 'Resource' tab in the top ribbon and selecting 'Leveling Options' from the Level group section.
Does resource leveling change the duration of my tasks?
No, resource leveling only delays the start date of a task or splits the task to fit the resource's schedule. It does not change the actual duration required to complete the work.