How to Determine the Critical Path After Resource Leveling in Microsoft Project
Question details
The user wants to identify the critical path of a project schedule accurately after applying resource leveling.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing an overallocated project schedule and attempting to evaluate the outcomes after leveling resources.
- Observed behavior
- Resource leveling alters task dates, dependencies, and available float, rendering the original critical path obsolete and producing multiple potential scheduling outcomes.
Ensure your project plan has a clean pre-leveling critical path by removing unnecessary date constraints, resolving missing task dependencies, and avoiding resource assignments on summary tasks.
Calculate Multiple Critical Paths After Leveling
Use the built-in advanced options to identify the newly calculated critical paths and float after leveling resources.
Because resource leveling delays certain tasks to resolve overallocations, the total float is consumed, changing the critical path. Calculating multiple critical paths helps you see the various paths driving different parts of your project.
Navigate to the File menu, select Options, and click on the Advanced tab. Scroll down to the calculation options for your project and check the box for 'Calculate multiple critical paths'.
If you want to find the critical path leading to one specific task, remove all successors from that particular task before calculating.
Go to the Resource tab on the ribbon and select 'Level All' to apply leveling to your overallocated resources.
Switch your view to see the Free Float and Total Float columns. Review the recalculated values to identify which tasks are now on the critical path.

Establish a Clean Pre-Leveling Schedule
Optimize the project file structure before applying resource leveling so the post-leveled results remain accurate and reliable.
Manage Project Schedules Effortlessly with WPS Office
While Microsoft Project handles complex resource leveling, WPS Office provides a free, lightweight alternative with powerful Spreadsheet tools. Use built-in Gantt chart templates to easily track your critical paths, task dates, and project milestones.

Frequently Asked Questions
Why does my critical path disappear after resource leveling?
Resource leveling delays tasks to resolve resource overallocations. This consumes total float, which can change which tasks are on the critical path or break the continuous path entirely depending on the schedule's constraints.
How can I find the critical path to one specific task?
In Microsoft Project, temporarily remove that specific task's successors. Then navigate to File > Options > Advanced, and check the 'Calculate multiple critical paths' box. The software will calculate the critical path leading directly up to that task.
Why is my post-leveled critical path chaotic or unreliable?
An unreliable post-leveled critical path usually results from a messy pre-leveling schedule. Common causes include resources assigned to summary tasks, open-ended tasks missing predecessors or successors, and excessive manual date constraints.