Fix a Missing Critical Path After Inactivating Tasks in Microsoft Project 2016
Question details
The user needs to understand why the critical path is no longer displayed after tasks are made inactive and how to review the schedule safely.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- Tasks have been marked inactive in a project schedule, including tasks that may affect the final task or schedule logic.
- Observed behavior
- The critical path may no longer appear after the tasks are inactivated.
Identify which tasks were recently made inactive and whether any are linked to the project’s final task. Use File > Save As to create a duplicate schedule for testing dependency changes.
Check Critical Task Display and Recalculate the Schedule
Use this first to rule out a display or calculation setting before changing task relationships.
Select View > Gantt Chart, and check that the task filter is set to show all tasks.
On the Gantt Chart Tools Format tab, select Critical Tasks to highlight critical bars.
Open File > Options > Schedule and check the setting for calculating the project after each edit. Enable automatic calculation if appropriate.
Press F9 to recalculate the schedule, then inspect the Gantt Chart for critical tasks.

Review Active Dependencies and the Project Finish
Use a duplicate schedule to investigate whether inactive tasks have interrupted the active path to the project finish.
Document Project Schedule Reviews with WPS Office
WPS Office is a free, lightweight alternative for documenting schedule reviews and sharing supporting files. Its familiar interface and Microsoft Office format compatibility make it easy to work with existing documents and spreadsheets. It does not fix Microsoft Project calculations or replace Project’s critical path scheduling.

Frequently Asked Questions
Why can inactivating tasks make the critical path disappear?
Inactive tasks are excluded from schedule calculations. If they affect dependencies leading to the project finish, the active schedule may no longer have the critical path you expect. Review the links in each task’s Task Information > Predecessors tab.
How do I show critical tasks in Microsoft Project 2016?
Open View > Gantt Chart, then select Critical Tasks on the Gantt Chart Tools Format tab. Also check that the active task filter is not hiding relevant tasks.
Should I change inactive tasks to zero duration?
No. Zero-duration tasks do not serve the same purpose as inactive tasks, and changing durations can make later reactivation difficult. Test schedule changes in a duplicate file and preserve the original durations.
Will pressing F9 restore the critical path?
F9 recalculates the project, but it cannot correct missing or inappropriate schedule dependencies. If the path still does not appear, inspect the active links leading to the final task.
Can WPS Office recalculate a Microsoft Project critical path?
No. Use Microsoft Project to inspect and recalculate the schedule. WPS Office can help document review notes in compatible Word or Excel files.