Fix a Missing Critical Path After Inactivating Tasks in Microsoft Project 2016

Emma BrownEmma Brown Nov 25, 2026 869 views

Question details

The user needs to understand why the critical path is no longer displayed after tasks are made inactive and how to review the schedule safely.

Fix a Missing Critical Path After Inactivating Tasks in Microsoft Project 2016
Product
Microsoft Project 2016
Device & OS
not provided
Scenario
Tasks have been marked inactive in a project schedule, including tasks that may affect the final task or schedule logic.
Observed behavior
The critical path may no longer appear after the tasks are inactivated.
Before you start

Identify which tasks were recently made inactive and whether any are linked to the project’s final task. Use File > Save As to create a duplicate schedule for testing dependency changes.

Solution 1Recommended

Check Critical Task Display and Recalculate the Schedule

Use this first to rule out a display or calculation setting before changing task relationships.

1
Open the Gantt Chart

Select View > Gantt Chart, and check that the task filter is set to show all tasks.

2
Show critical tasks

On the Gantt Chart Tools Format tab, select Critical Tasks to highlight critical bars.

3
Check calculation settings

Open File > Options > Schedule and check the setting for calculating the project after each edit. Enable automatic calculation if appropriate.

4
Recalculate the project

Press F9 to recalculate the schedule, then inspect the Gantt Chart for critical tasks.

Check Critical Task Display and Recalculate the Schedule
A display check may not be enough: Inactive tasks are excluded from schedule calculations. If they interrupt the logic leading to the project finish, recalculation alone may not restore the expected critical path.
Free Microsoft Office alternative

Document Project Schedule Reviews with WPS Office

WPS Office is a free, lightweight alternative for documenting schedule reviews and sharing supporting files. Its familiar interface and Microsoft Office format compatibility make it easy to work with existing documents and spreadsheets. It does not fix Microsoft Project calculations or replace Project’s critical path scheduling.

Record inactive tasks and dependency review notes in a spreadsheetWorks with Microsoft Word and Excel formats, including DOCX and XLSXFamiliar interface for an easier move from Microsoft OfficeFree and lightweight tools for everyday documents and spreadsheets
microsoft office alternative - wps office

Frequently Asked Questions

Why can inactivating tasks make the critical path disappear?

Inactive tasks are excluded from schedule calculations. If they affect dependencies leading to the project finish, the active schedule may no longer have the critical path you expect. Review the links in each task’s Task Information > Predecessors tab.

How do I show critical tasks in Microsoft Project 2016?

Open View > Gantt Chart, then select Critical Tasks on the Gantt Chart Tools Format tab. Also check that the active task filter is not hiding relevant tasks.

Should I change inactive tasks to zero duration?

No. Zero-duration tasks do not serve the same purpose as inactive tasks, and changing durations can make later reactivation difficult. Test schedule changes in a duplicate file and preserve the original durations.

Will pressing F9 restore the critical path?

F9 recalculates the project, but it cannot correct missing or inappropriate schedule dependencies. If the path still does not appear, inspect the active links leading to the final task.

Can WPS Office recalculate a Microsoft Project critical path?

No. Use Microsoft Project to inspect and recalculate the schedule. WPS Office can help document review notes in compatible Word or Excel files.