Question details

The user wants to display the critical path in a Microsoft Project 2016 Gantt chart.

How to Show the Critical Path in a Microsoft Project 2016 Gantt Chart
Product
Microsoft Project 2016
Device & OS
not provided
Scenario
The user is reviewing a project schedule and wants to identify the tasks that determine its finish date.
Observed behavior
The critical path may not appear even when critical-task formatting and filters are enabled.
Before you start

Open the project in Gantt Chart view and identify the tasks that should determine the project finish date. Check whether they have durations and logical predecessor relationships.

Solution 1Recommended

Check task scheduling, dependencies, and slack

Use this method when critical-task formatting is enabled but the expected path is missing.

Project calculates critical tasks from the schedule, including dependencies, constraints, and slack. Highlighting or filtering critical tasks will not create missing dependencies.

1
Use automatic scheduling

In Gantt Chart view, select the relevant regular tasks, then choose Task > Auto Schedule. Avoid manually entering Start and Finish dates unless the schedule requires them.

2
Link related tasks

Select a predecessor task and its successor in the order they should occur, then choose Task > Link Tasks. Repeat for the logical sequence of work, and review the links in the Predecessors column.

3
Inspect total slack

Right-click a column heading, choose Insert Column, and select Total Slack. Under the default critical-task setting, tasks with zero or negative total slack are critical.

4
Review constraints

Double-click a task and open the Advanced tab in Task Information. Check whether a constraint date or constraint type is affecting the schedule, and change it only if it does not reflect a real scheduling requirement.

Check task scheduling, dependencies, and slack
Slack thresholds can differ: The default critical threshold is zero days, but it can be changed under File > Options > Advanced. Negative slack can also indicate a critical task.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for maintaining project task lists and timelines in spreadsheets. Open compatible Excel files to continue working with existing task data. WPS does not replace Microsoft Project's critical-path calculation.

Organize project tasks, dates, and dependencies in a spreadsheetOpen and edit Microsoft Excel XLSX files for easier migrationUse a familiar spreadsheet interface with common formatting toolsWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why is my critical path not showing in Project 2016?

The relevant tasks may be manually scheduled, missing dependencies, or have positive total slack. Check Task > Auto Schedule, review the Predecessors column, and insert the Total Slack column before turning on Critical Tasks formatting.

How do I show critical tasks in a Gantt chart?

Open View > Gantt Chart, then select Critical Tasks on the Gantt Chart Tools Format tab. You can also select Critical from the Filter list on the View tab.

Are tasks with zero slack always critical?

By default, Project marks tasks with zero or negative total slack as critical. The threshold can be changed under File > Options > Advanced, so check that setting if the results differ.