Show the Critical Path in a Microsoft Project 2016 Gantt Chart
Question details
The user wants to display the critical path in a Microsoft Project 2016 Gantt chart.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- The user is reviewing a project schedule and wants to identify the tasks that determine its finish date.
- Observed behavior
- The critical path may not appear even when critical-task formatting and filters are enabled.
Open the project in Gantt Chart view and identify the tasks that should determine the project finish date. Check whether they have durations and logical predecessor relationships.
Check task scheduling, dependencies, and slack
Use this method when critical-task formatting is enabled but the expected path is missing.
Project calculates critical tasks from the schedule, including dependencies, constraints, and slack. Highlighting or filtering critical tasks will not create missing dependencies.
In Gantt Chart view, select the relevant regular tasks, then choose Task > Auto Schedule. Avoid manually entering Start and Finish dates unless the schedule requires them.
Select a predecessor task and its successor in the order they should occur, then choose Task > Link Tasks. Repeat for the logical sequence of work, and review the links in the Predecessors column.
Right-click a column heading, choose Insert Column, and select Total Slack. Under the default critical-task setting, tasks with zero or negative total slack are critical.
Double-click a task and open the Advanced tab in Task Information. Check whether a constraint date or constraint type is affecting the schedule, and change it only if it does not reflect a real scheduling requirement.

Highlight or filter critical tasks in the Gantt chart
Use this after checking that Project has calculated the expected critical tasks.
Track Project Tasks in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for maintaining project task lists and timelines in spreadsheets. Open compatible Excel files to continue working with existing task data. WPS does not replace Microsoft Project's critical-path calculation.

Frequently Asked Questions
Why is my critical path not showing in Project 2016?
The relevant tasks may be manually scheduled, missing dependencies, or have positive total slack. Check Task > Auto Schedule, review the Predecessors column, and insert the Total Slack column before turning on Critical Tasks formatting.
How do I show critical tasks in a Gantt chart?
Open View > Gantt Chart, then select Critical Tasks on the Gantt Chart Tools Format tab. You can also select Critical from the Filter list on the View tab.
Are tasks with zero slack always critical?
By default, Project marks tasks with zero or negative total slack as critical. The threshold can be changed under File > Options > Advanced, so check that setting if the results differ.
Can WPS Office calculate the critical path in a Project file?
WPS Spreadsheets can help organize task data in an Excel-compatible workbook, but it does not replace Microsoft Project's critical-path calculation. Use Project to calculate and display the path.