Show Task Names on Gantt Bars in Microsoft Project 2016
Question details
The user wants task, summary task, and milestone names to appear beside Gantt bars in Microsoft Project 2016.

- Product
- Microsoft Project 2016
- Device & OS
- not provided
- Scenario
- A project uses manually scheduled tasks, and the user wants to identify tasks directly on the Gantt Chart.
- Observed behavior
- Task, summary task, and milestone names do not automatically appear beside their Gantt bars.
Open the project in Microsoft Project 2016 and switch to the Gantt Chart view. Check which tasks are manually scheduled so you can update the relevant bar styles.
Add task names to the applicable Gantt bar styles
Use Bar Styles to show the Name field beside manual, rolled-up, summary, and milestone bars.
In the Gantt Chart view, double-click a blank area of the chart pane to open the Bar Styles dialog.
In the style list, select Task, then open the Text tab or Text section.
Set the Right text position to Name to display the task name to the right of the bar.
Repeat the Text setting for Rolled Up Task, Manual Task, Manual Task (Warning), and Rolled Up Manual Task. Also update the applicable summary and milestone styles if their names are needed.
Click OK and check the Gantt Chart to confirm that the names appear beside the relevant bars.

Track project tasks in WPS Spreadsheets
WPS Office is a free, lightweight alternative for tracking project tasks in a familiar spreadsheet interface. Open compatible Excel files to move task lists into WPS Spreadsheets. WPS does not change Microsoft Project Gantt bar settings.

Frequently Asked Questions
Why do some task names still not appear after I edit the Task style?
Different bars can use different styles. In Bar Styles, set the Right text position to Name for the applicable manual, rolled-up, summary, and milestone styles as well.
Can I place the task name somewhere other than the right side of the bar?
Yes. In the Bar Styles dialog, select a style and use its Text section to choose another available position for the Name field.
Why does a new manual task's bar have no name label?
The label may not appear until the task has a duration. Enter a duration in the Gantt Chart task table, then check that the applicable manual-task style has Name set in its Text section.
Will WPS Office change the bar styles in my Microsoft Project file?
No. Change Gantt bar styles in Microsoft Project. For an alternative task list, use WPS Spreadsheets with an Excel-compatible XLSX file.