Fix a Critical Path Not Displaying Correctly in Microsoft Project
Question details
The user needs Microsoft Project to show a connected, accurately calculated critical path.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project uses manually scheduled summary and detail tasks, and some detail tasks extend beyond their summary task dates.
- Observed behavior
- Gantt bars appear red, but they do not form the expected connected critical path.
Open the project in Gantt Chart view and check whether detailed tasks extend beyond their summary task dates. Review the Task Mode column to identify manually scheduled tasks.
Recalculate Summary Dates and Link Automatically Scheduled Tasks
Use automatic scheduling and task dependencies to correct summary dates and build a reliable critical path.
Manually scheduled summary tasks can retain dates that do not reflect their subtasks. Automatically scheduled summary tasks calculate their dates from the tasks beneath them.
In Gantt Chart view, open the View tab and use the Filter menu to select Summary Tasks. If it is not listed, look under More Filters.
Select the summary task rows, then choose Task > Auto Schedule. Check that each summary bar now covers its detailed tasks.
Use View > Filter > No Filter to show all tasks. Select the relevant detail tasks and milestones, then choose Task > Auto Schedule so Project can calculate their dates from the schedule.
Select tasks or milestones in their intended sequence and choose Task > Link Tasks. Review each dependency and adjust its type or lag as needed in the task information.
In Gantt Chart view, open the Format tab and select Critical Tasks. Review the red bars and their dependency links to confirm that the critical path reflects the intended sequence.

Review Constraints and Slack Settings
Use this check if the critical path still looks unexpected after dates and dependencies are corrected.
Use WPS Office for Project Reports and Schedule Tables
WPS Office is a free, lightweight alternative for working with project reports and schedule tables. Its familiar interface and Microsoft Office format compatibility make it easy to move common documents and spreadsheets between suites. It does not repair Microsoft Project critical-path calculations.

Frequently Asked Questions
Why do red Gantt bars not form a connected critical path?
Red bars identify tasks considered critical, but missing dependencies, manual dates, constraints, or incorrect summary dates can make the result look disconnected. Check task links and scheduling modes in Gantt Chart view.
How do I turn on critical task highlighting?
Open Gantt Chart view, select the Format tab, and check Critical Tasks. Project will highlight tasks that meet its critical slack threshold.
Why does a subtask extend beyond its summary bar?
A manually scheduled summary task can retain dates that do not cover its subtasks. Select the summary row and choose Task > Auto Schedule to calculate its dates from the subtasks.
Should I use constraints instead of dependencies?
Use dependencies to represent the order of work. Apply constraints only when a scheduling requirement calls for them, because they can affect task dates, slack, and the calculated critical path.