Fix an Incomplete Critical Path in Microsoft Project 2019

Aamir Naveed AkramAamir Naveed Akram Nov 13, 2026 870 views

Question details

The user needs to understand why Microsoft Project 2019 displays a critical path for only part of a project and how to verify the schedule.

Fix an Incomplete Critical Path in Microsoft Project 2019
Product
Microsoft Project 2019
Device & OS
not provided
Scenario
Reviewing the project's critical path and checking whether task relationships and scheduling settings produce the expected result.
Observed behavior
Only part of the project appears critical. Task dependencies, summary-task relationships, slack values, or critical-task settings may explain the result.
Before you start

Open the project in Gantt Chart view and expand the summary tasks so individual tasks are visible. Clear any task filter and show the Predecessors and Successors columns before assessing the dependency network.

Solution 1Recommended

Check individual task links and remove inappropriate summary-task dependencies

Use this check when the visible schedule contains mainly summary tasks or the dependency chain appears incomplete.

Summary tasks organize and roll up their subtasks. Build the scheduling network with individual tasks and milestones rather than using summary tasks as predecessors or successors.

1
Expand the task outline

Open View > Gantt Chart. On the View tab, use Outline > All Subtasks to display the tasks beneath each summary row.

2
Show task relationships

Right-click a column heading, select Insert Column, and add Predecessors. Repeat to add Successors so you can inspect both sides of each task relationship.

3
Replace summary-task links

Review summary rows for predecessor or successor entries. Double-click the affected task and open the Predecessors tab to remove inappropriate links, then create the intended relationship between the relevant individual tasks or milestones.

4
Check the dependency network

Inspect the Predecessors and Successors columns for missing or unintended relationships. Add links that reflect actual work dependencies, and confirm that tasks intended to affect project completion connect to the appropriate downstream work or finish milestone.

Check individual task links and remove inappropriate summary-task dependencies
Do not link tasks just to make them critical: A starting task may legitimately have no predecessor, and a finishing task may have no successor. Add only real dependencies; not every project task should be critical.
Free Microsoft Office alternative

Use WPS Spreadsheet for Lightweight Project Task Tracking

WPS Office is a free, lightweight, easy-to-use Office alternative for tracking tasks, dates, and status in spreadsheets. Its familiar interface and Excel-format compatibility make migrating spreadsheet-based project reports straightforward. It does not fix Microsoft Project's critical-path calculation or replace its scheduling engine.

Organize project tasks, owners, start dates, finish dates, and progress in WPS Spreadsheet.Open and edit Microsoft Excel .xlsx and .xls files for spreadsheet-based project reporting.Use a familiar spreadsheet interface to move existing Excel task trackers into WPS.Create simple project status reports without requiring a dedicated scheduling application.
microsoft office alternative - wps office

Frequently Asked Questions

Why does Microsoft Project mark only some tasks as critical?

Critical tasks are determined by total slack and the threshold under File > Options > Advanced > Calculation options for this project. Tasks with slack above that threshold are not critical, so highlighting only part of the schedule may be correct.

Should I link summary tasks to other tasks?

For this troubleshooting workflow, build dependencies between individual tasks and milestones instead. Expand the outline in View > Outline > All Subtasks, then inspect the Predecessors and Successors columns for summary-task links that should be replaced.

Where can I see the slack values used for critical-path analysis?

In Gantt Chart view, go to View > Tables > More Tables, select Schedule, and click Apply. The Schedule table includes early and late dates, Free Slack, and Total Slack. Total Slack is the key value to compare with the critical-task threshold.

What should I show when asking someone to review my critical path?

Expand the individual tasks and include task names, dates, Predecessors, Successors, and Total Slack in the view. A screenshot containing only summary tasks does not provide enough detail to assess the dependency network.

Can WPS Office recalculate a Microsoft Project critical path?

WPS Spreadsheet is not a replacement for Microsoft Project's scheduling engine. Use Microsoft Project to correct dependencies and recalculate the critical path; use WPS Spreadsheet for Excel-format task lists and project status reports.