Question details

The user needs to understand why some tasks are missing from the critical path highlight in Microsoft Project.

Fix an Incomplete Critical Path Highlight in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Reviewing the critical path in a project where linked tasks use different working calendars.
Observed behavior
Some tasks are not highlighted as critical because calendar differences can leave them with a small amount of positive total slack.
Before you start

Open the project in Microsoft Project and identify a task you expect to see on the critical path. Check whether it and its successor use different working calendars.

Solution 1Recommended

Inspect calendar gaps and adjust the critical slack threshold

Use this method when linked tasks have small amounts of total slack caused by different working calendars.

1
Display dates and times

Go to File > Options > General and choose a date format that displays both the date and time. Compare the finish time of the missing task with the start time of its successor.

2
Check total slack

Open View > Tables > Schedule and inspect the Total Slack field for the task. A small positive value may correspond to a gap between the tasks' working calendars.

3
Review task calendars

Open Task Information for each linked task and check its calendar on the Advanced tab. Compare the working times, including weekends, to understand where the gap comes from.

4
Adjust the threshold

Go to File > Options > Advanced and find the setting for tasks being critical when slack is less than or equal to a specified number of days. Increase it from 0 to the amount needed, such as 1 or 2 days, and select OK.

5
Check the highlight

In the Gantt Chart view, select Format > Critical Tasks and verify that the expected task is highlighted.

Inspect calendar gaps and adjust the critical slack threshold
Review other highlighted tasks: A higher threshold can also mark tasks with genuine schedule flexibility as critical. It changes which tasks are classified as critical; it does not remove the calendar gap.
Free Microsoft Office alternative

Use WPS Office for Project Reports and Schedule Tables

WPS Office is a free, lightweight Office alternative with a familiar interface and Microsoft Office format compatibility, making it easy to move existing reports and spreadsheets. It does not change Microsoft Project critical-path settings.

Organize project schedule tables and reports in WPS SpreadsheetsOpen and edit Microsoft Excel XLSX and Word DOCX filesWork in a familiar, easy-to-use interfaceUse a free, lightweight office suite for everyday documents
microsoft office alternative - wps office

Frequently Asked Questions

Why is a linked task missing from the critical path?

Different task calendars can create a gap and give the task positive total slack. Open View > Tables > Schedule and check its Total Slack value.

How do I show the time as well as the date in Microsoft Project?

Go to File > Options > General and select a date format that includes the time. This makes small gaps between linked tasks easier to see.

Where can I change the critical slack threshold?

Go to File > Options > Advanced and find the setting that defines tasks as critical when their slack is less than or equal to a specified number of days.

Will increasing the threshold fix the calendar gap?

No. It changes which tasks are classified and highlighted as critical. Review the task calendars and relationships if the gap itself needs to be changed.