Fix Microsoft Project Summary Task Dates After Adding Resources

Jason MillerJason Miller Nov 27, 2026 869 views

Question details

Correct summary task dates that do not recalculate after resources and work are added.

Fix Microsoft Project Summary Task Dates After Adding Resources
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
Resources and work have been assigned to tasks, changing their durations according to resource working hours.
Observed behavior
Task durations change, but summary task dates remain incorrect or do not recalculate.
Before you start

Open the project in Gantt Chart view and identify the affected summary task and its subtasks. Check their Task Mode indicators before changing scheduling settings.

Solution 1Recommended

Set the summary task and its subtasks to Auto Scheduled

Use automatic scheduling so the summary dates can reflect the dates of its subtasks.

1
Select the affected tasks

In Gantt Chart view, select the affected summary task and its subtasks using their row numbers. You can also select all tasks if you want the entire project to use automatic scheduling.

2
Enable automatic scheduling

On the Task ribbon, click Auto Schedule. Confirm that the Task Mode indicators for the selected tasks show automatic scheduling.

3
Check the summary dates

Review the Start and Finish columns for the summary task and its subtasks. An automatically scheduled summary task should reflect the earliest start and latest finish of its subtasks.

Set the summary task and its subtasks to Auto Scheduled
Review the effects: Changing task modes can alter scheduled dates. If the affected tasks are already automatically scheduled, check calendars and calculation settings instead.
Free Microsoft Office alternative

Use WPS Office for Project Reports and Schedule Spreadsheets

WPS Office is a free, lightweight alternative for working with project reports and schedule spreadsheets in a familiar interface. Its Microsoft Office format support makes it easy to move common documents between suites, but it does not fix Microsoft Project scheduling or recalculate an MPP project.

Organize project dates and status reports in WPS SpreadsheetsWork with Microsoft Excel XLSX and Word DOCX filesUse a familiar interface for everyday document editingMove common Office documents between applications with ease
microsoft office alternative - wps office

Frequently Asked Questions

Why does a summary task have different dates from its subtasks?

A manually scheduled summary task can retain dates that differ from its subtasks. Select the summary task and click Auto Schedule on the Task ribbon to let Project calculate its dates from the subtasks.

Why did a task's duration change when I added a resource?

Duration can change because of the resource's working hours, assigned work, task type, or effort-driven setting. Double-click the task and check the Advanced tab in Task Information, then review its assignments in Task Usage view.

How do I force Microsoft Project to recalculate?

Press F9 to calculate the project. To calculate after edits automatically, go to File > Options > Schedule and set Calculate project after each edit to On.

Can WPS Office fix dates in a Microsoft Project MPP file?

No. Use Microsoft Project to check task modes, calendars, and calculation settings. WPS Spreadsheets can be used separately for project reports or schedules in Excel-compatible files.