Display milestone diamonds from subtasks on their summary task in Project 2013.

Roll Up Milestones to a Summary Task in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A user wants milestone subtasks to appear on the summary task bar in a Gantt chart.
Observed behavior
The user cannot find the Roll up Gantt bars option used in Project 2007.
Before you start

Open the project in Gantt Chart view and identify the milestone subtasks and their intended summary task.

Solution 1Recommended

Enable Rollup for Each Milestone Subtask

Use the Rollup field to show milestone subtasks on their summary task.

1
Check the task hierarchy

In View > Gantt Chart, confirm that each milestone is indented beneath the correct summary task. Select a milestone and use Task > Indent Task if needed.

2
Add the Rollup field

Right-click a column heading in the task table, select Insert Column, and choose Rollup.

3
Enable milestone rollup

In the Rollup column, set each milestone subtask to Yes. Repeat for every milestone you want to show on the summary bar.

4
Check summary scheduling

Select the summary task and choose Task > Auto Schedule if it is manually scheduled. Check the summary bar in the Gantt chart for the milestone diamonds.

Enable Rollup for Each Milestone Subtask
Display settings: If the diamonds are still hidden, check the Gantt chart formatting options for a Rollup display setting and make sure rollups are shown.
Free Microsoft Office alternative

Track Project Milestones in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface and Microsoft Office format compatibility for an easier migration. Use WPS Spreadsheets to maintain a milestone tracking table; it does not change Microsoft Project rollup settings.

Create a milestone tracking table with dates and statusOpen and edit Microsoft Excel XLS and XLSX filesWork in a familiar spreadsheet interfaceUse a free, lightweight Office alternative
microsoft office alternative - wps office

Frequently Asked Questions

Where is the rollup setting in Project 2013?

In Gantt Chart view, right-click a task-table column heading, choose Insert Column, and select Rollup. Set the field to Yes for each milestone you want to roll up.

Why is my milestone not appearing on the summary task?

Check that the milestone is indented beneath the correct summary task and its Rollup field is set to Yes. Also check the summary task's scheduling mode and the Gantt chart's rollup display settings.

How do I make the summary task automatically scheduled?

Select the summary task in the task table, then choose Task > Auto Schedule. Review the Gantt chart after changing the scheduling mode.

Does WPS Office change Project 2013 rollup settings?

No. Change the Rollup field in Microsoft Project. WPS Spreadsheets can be used separately to track milestones in a spreadsheet.