Fix a Wrong Summary Task Actual Start Date in Microsoft Project 2013
Question details
Find out why a summary task shows an actual start date earlier than the date entered for its completed child task.

- Product
- Microsoft Project 2013
- Device & OS
- not provided
- Scenario
- A summary task has an earlier actual start date than its only known completed child task, possibly after out-of-sequence work or a project update.
- Observed behavior
- The summary task displays an actual start date earlier than the completed child task's actual start date.
Open the affected project in Microsoft Project 2013 and identify the summary task and its child tasks. Check the reporting date you intend to use before changing any scheduling or progress settings.
Inspect All Child Tasks and Their Actual Start Dates
Use this check to find hidden or previously updated tasks that may explain the earlier summary date.
Open View > Gantt Chart, expand the affected summary task, and show all subtasks in its outline.
On the View tab, set Filter to No Filter and Group By to No Group so tasks are less likely to be hidden.
Right-click a column heading, choose Insert Column, and add Actual Start. Compare the summary date with the dates on all child tasks, including zero-duration tasks and tasks updated previously.
Select any child task with an earlier actual date and review its progress and actual dates. Correct an entry only if it does not reflect the work performed.

Review the Status Date and Update Project Settings
Use this method if Update Project was used to record progress or move uncompleted work.
Check Dependencies and Out-of-Sequence Work
Use this check when actual work started in a different order from the planned schedule.
Review Project Data in WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface. Export project data to an Excel workbook to review dates in WPS Spreadsheets and migrate spreadsheet-based reports easily. WPS does not fix Microsoft Project scheduling calculations.

Frequently Asked Questions
Why is the summary task's actual start earlier than the completed task's date?
Another child or nested task may have an earlier actual start, even if it is hidden or was updated previously. Expand the outline, clear filters, and add the Actual Start column to compare all child tasks.
Where can I check the project status date?
In Microsoft Project 2013, open Project > Project Information and review the Status date. Compare it with the reporting period used for task updates.
Can Update Project change task scheduling?
Yes. The option to reschedule uncompleted work can change task dates and may introduce constraints. Check the options under Project > Update Project and inspect the Constraint Type and Constraint Date columns afterward.
Can WPS Office correct the summary date in Microsoft Project?
No. Correct the scheduling or progress data in Microsoft Project. You can export project data to an Excel workbook and use WPS Spreadsheets to review the dates separately.