Fix a Wrong Summary Task Actual Start Date in Microsoft Project 2013

Emma BrownEmma Brown Nov 27, 2026 868 views

Question details

Find out why a summary task shows an actual start date earlier than the date entered for its completed child task.

Fix a Wrong Summary Task Actual Start Date in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A summary task has an earlier actual start date than its only known completed child task, possibly after out-of-sequence work or a project update.
Observed behavior
The summary task displays an actual start date earlier than the completed child task's actual start date.
Before you start

Open the affected project in Microsoft Project 2013 and identify the summary task and its child tasks. Check the reporting date you intend to use before changing any scheduling or progress settings.

Solution 1Recommended

Inspect All Child Tasks and Their Actual Start Dates

Use this check to find hidden or previously updated tasks that may explain the earlier summary date.

1
Show the task outline

Open View > Gantt Chart, expand the affected summary task, and show all subtasks in its outline.

2
Clear filters and grouping

On the View tab, set Filter to No Filter and Group By to No Group so tasks are less likely to be hidden.

3
Display actual dates

Right-click a column heading, choose Insert Column, and add Actual Start. Compare the summary date with the dates on all child tasks, including zero-duration tasks and tasks updated previously.

4
Review unexpected entries

Select any child task with an earlier actual date and review its progress and actual dates. Correct an entry only if it does not reflect the work performed.

Inspect All Child Tasks and Their Actual Start Dates
Check the full outline: A task can affect the summary even if it was not the completed child task you expected to find. Look for nested subtasks as well as direct children.
Free Microsoft Office alternative

Review Project Data in WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface. Export project data to an Excel workbook to review dates in WPS Spreadsheets and migrate spreadsheet-based reports easily. WPS does not fix Microsoft Project scheduling calculations.

Review exported task dates and progress in a spreadsheetCompatible with Microsoft Excel XLSX workbooksFamiliar spreadsheet interface for reviewing Office filesFree and lightweight for everyday document work
microsoft office alternative - wps office

Frequently Asked Questions

Why is the summary task's actual start earlier than the completed task's date?

Another child or nested task may have an earlier actual start, even if it is hidden or was updated previously. Expand the outline, clear filters, and add the Actual Start column to compare all child tasks.

Where can I check the project status date?

In Microsoft Project 2013, open Project > Project Information and review the Status date. Compare it with the reporting period used for task updates.

Can Update Project change task scheduling?

Yes. The option to reschedule uncompleted work can change task dates and may introduce constraints. Check the options under Project > Update Project and inspect the Constraint Type and Constraint Date columns afterward.

Can WPS Office correct the summary date in Microsoft Project?

No. Correct the scheduling or progress data in Microsoft Project. You can export project data to an Excel workbook and use WPS Spreadsheets to review the dates separately.