Update the Start Time of All Tasks in Microsoft Project 2013

Khadija KhanKhadija Khan Nov 27, 2026 868 views

Question details

Update approximately 2,000 tasks to start at 9:00 AM without editing each task individually.

Update the Start Time of All Tasks in Microsoft Project 2013
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A project uses working hours of 9:00 AM–12:00 PM and 1:00 PM–6:00 PM, and the user wants a consistent start time for its tasks.
Observed behavior
Tasks currently start at different times despite the intended working hours.
Before you start

In File > Options > General, choose a date format that displays the time so you can inspect task and project start times. Check whether tasks have dependencies, assigned resources, progress, or fixed constraints that could affect their scheduled starts.

Solution 1Recommended

Align the project calendar and recalculate eligible tasks

Use the project calendar, scheduling defaults, and bulk task settings to correct start times where the schedule permits.

A 9:00 AM working-day start does not guarantee that every task starts at 9:00 AM. Dependencies, durations, resource calendars, progress, and other scheduling settings can place a task later in the day.

1
Check the project start

Open Project > Project Information. Confirm that the project is scheduled from its start date, select the intended project calendar, and set the start date and time to 9:00 AM if appropriate.

2
Set working hours

Go to Project > Change Working Time. Select the project calendar, open the Work Weeks tab, and use Details to set the applicable working days to 9:00 AM–12:00 PM and 1:00 PM–6:00 PM.

3
Match scheduling defaults

Open File > Options > Schedule. Set Default start time to 9:00 AM and Default end time to 6:00 PM; confirm that Hours per day is 8. These defaults do not by themselves force existing tasks to start at 9:00 AM.

4
Review task constraints in bulk

In the Gantt Chart, select the eligible task rows, then open Task > Information. On the Advanced tab, set Constraint type to As Soon As Possible where appropriate. Review tasks that need fixed dates before changing their constraints.

5
Recalculate eligible tasks

Select the tasks that should be automatically scheduled and choose Task > Auto Schedule. Review the Start column and inspect dependencies, resource calendars, and progress for tasks that still begin after 9:00 AM.

Align the project calendar and recalculate eligible tasks
A uniform start time is not always compatible with the schedule: Automatically scheduled tasks follow their dependencies and applicable calendars. Forcing every task to begin at 9:00 AM may require changing those relationships or other scheduling conditions.
Free Microsoft Office alternative

Use WPS Office for project-related spreadsheets and documents

WPS Office is a free, lightweight, easy-to-use alternative for project documents and spreadsheets, with a familiar interface and Microsoft Office format compatibility to support migration. It does not change Microsoft Project task schedules or replace Microsoft Project for editing MPP files.

Track project information in spreadsheets alongside your Project scheduleWork with Microsoft Word, Excel, and PowerPoint formatsUse a familiar interface for everyday document editingMove common Office documents into a lightweight suite
microsoft office alternative - wps office

Frequently Asked Questions

Why do some tasks still start after 9:00 AM?

A predecessor may finish during the workday, or a resource calendar, constraint, or recorded progress may affect the task. Check the task's predecessors and assigned resources in the Gantt Chart and Task Information.

Does changing the default start time update every existing task?

No. File > Options > Schedule controls scheduling defaults, but changing the default start time alone does not force existing tasks to start at that time.

How can I see the time in the Start column?

Go to File > Options > General and select a date format that includes the time. Then review the Start column in the Gantt Chart.

Can I change multiple tasks from manual to automatic scheduling?

Yes. Select the eligible task rows in the Gantt Chart and choose Task > Auto Schedule. Review the resulting dates because Project will recalculate them using the applicable scheduling rules.