Fix Start-to-Finish Date Mismatches in Microsoft Project

Huda QurayshiHuda Qurayshi Nov 27, 2026 868 views

Question details

Determine why a two-day task appears to finish on Day Zero rather than at the end of the previous working day.

Fix Start-to-Finish Date Mismatches in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A plan is built around an externally supplied Day Zero date, and external resource calculations depend on the displayed finish date.
Observed behavior
A task linked with a Start-to-Finish relationship appears to finish at 8:00 a.m. on Day Zero instead of 5:00 p.m. on the previous working day.
Before you start

Identify the externally supplied Day Zero task, the affected two-day task, and the relationship between them. Confirm the expected working hours and whether downstream calculations use the finish date, time, or both.

Solution 1Recommended

Check the Start-to-Finish link and working-time settings

Use this approach to understand the displayed finish time before changing a plan that depends on Day Zero.

In a Start-to-Finish relationship, the successor cannot finish before its predecessor starts. If Day Zero is the predecessor starting at 8:00 a.m., the linked task may finish at that boundary, even though its two days of work fall on earlier working days.

The previous working day's 5:00 p.m. and Day Zero's 8:00 a.m. can be separated by nonworking time. They are different timestamps, so a date-based external calculation may still treat them differently.

1
Display dates and times

Open File > Options > General and choose a date format that includes the time. Review the Start and Finish columns for the affected task and Day Zero.

2
Inspect the link

Double-click the affected task, open Task Information > Predecessors, and check which task is the predecessor, the relationship type, and any lag or lead. Confirm that the Start-to-Finish direction reflects the intended dependency.

3
Review calendars

Open Project > Change Working Time to check working hours and exceptions. Also inspect the task calendar in Task Information > Advanced and any assigned resource calendars.

4
Check scheduling controls

Review the Task Mode column and Task Information > Advanced for each relevant task. Check whether manual scheduling or a date constraint is affecting the result.

5
Check the external calculation

Inspect the exported Finish field and the downstream calculation's date and time rules. If a previous-working-day reporting date is required, define that conversion explicitly rather than assuming the displayed finish timestamp already provides it.

Check the Start-to-Finish link and working-time settings
A displayed date may not be a scheduling error: Do not change the task's actual finish solely to alter a report date. Agree on how the external calculation should handle working-time boundaries and nonworking days.
Free Microsoft Office alternative

Review Project Schedule Exports in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for reviewing schedule data exported to spreadsheets. It supports common Office formats for an easier move between applications, but it does not replace Microsoft Project's scheduling engine.

Review exported task dates and times in WPS SpreadsheetsOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface to share schedule reportsWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does the task finish at 8:00 a.m. on Day Zero?

A Start-to-Finish link can place the successor's finish at the predecessor's start. Check Task Information > Predecessors and display times in File > Options > General to see the relationship and timestamps.

Does 8:00 a.m. on Day Zero mean work happened that morning?

Not necessarily. If the calendar has no working time between the prior day's end and Day Zero's start, the task's work may fall entirely on earlier working days. Check Project > Change Working Time and the assigned resource calendars.

How can I make an external report use the previous working date?

Check how the report reads the exported Finish field, then define an agreed conversion for working-time boundaries using the relevant calendar. Do not assume that changing the display format changes the underlying timestamp.

Should I replace every Start-to-Finish link with Finish-to-Start?

No. Review each dependency in Task Information > Predecessors and choose the relationship that reflects the real sequence. Finish-to-Start is often clearer for sequential work, but changing links can alter the schedule.

Can WPS Office recalculate my Microsoft Project schedule?

No. Use Microsoft Project to calculate task relationships, calendars, and constraints. You can export schedule data to an Excel file and review it in WPS Spreadsheets.