Fix Microsoft Project Task Start and Finish Dates
Question details
The user needs to change a task's start or finish date without unexpected constraints or changes to predecessor dates.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Editing dates and dependencies in an automatically scheduled project.
- Observed behavior
- Project adds constraints or changes a predecessor's date, and the task cannot be moved before a particular date.
Identify the affected task, its intended dates, and any predecessor that moves unexpectedly. Check whether the task is automatically or manually scheduled in the Task Mode column.
Review the project schedule, task constraints, and dependencies
Use this approach to find scheduling rules that prevent the task from moving or cause a linked task to move.
Open Project > Project Information. Check the project start or finish date and whether the project is scheduled from its start date or finish date; correct these settings if they do not match your plan.
Double-click the affected task and open the Advanced tab in Task Information. Review Constraint type and Constraint date, and replace any unintended fixed-date constraint with a flexible option appropriate to the project's scheduling direction.
In Task Information, open the Predecessors tab and check each linked task, dependency type, and lag. Correct or remove unintended links, then inspect linked successor tasks for constraints that may also affect the schedule.
Open Project > Change Working Time to review the project calendar and nonworking dates. In Task Information > Advanced, check for a task calendar; also review assigned resource calendars if resources are affecting the task.
Select the task and use Task > Inspect Task, if available, to see factors driving its dates. Reenter the intended date in the Start or Finish column and check the task and its linked tasks for the expected result.

Test the project file by reopening an XML copy
Try this if the scheduling settings and links appear correct but Project still changes dates unexpectedly.
Use WPS Office for project documents and schedules
WPS Office is a free, lightweight Office alternative with a familiar interface for project documents and spreadsheet schedules. It supports common Microsoft Office formats for easier migration, but it does not fix Microsoft Project scheduling or replace its scheduling engine.

Frequently Asked Questions
Why does Microsoft Project add a constraint when I enter a task date?
For an automatically scheduled task, entering a date can create a scheduling constraint. Double-click the task and check Constraint type and Constraint date on the Advanced tab.
Why does changing a task affect its predecessor?
Dependencies, constraints, and the project's scheduling direction can influence linked task dates. Check Project > Project Information and review the affected task's Predecessors tab and linked tasks.
Where can I see what is driving a task's date?
Select the task and choose Task > Inspect Task, if available. Also check its constraint, predecessors, and calendar in Task Information.
Can a calendar stop a task from starting on a particular day?
Yes. Nonworking time in the project, task, or assigned resource calendar can affect scheduling. Check Project > Change Working Time and the task calendar on the Advanced tab of Task Information.
Will reopening an XML copy fix a corrupted project?
It may help identify or work around a file-specific problem, but it is not a guaranteed repair. Use File > Save As to create an XML copy, reopen it, and verify the schedule and important data.