Make a Successor Task Start After Its Predecessor in Microsoft Project

Muhammad TalhaMuhammad Talha Nov 14, 2026 868 views

Question details

The user wants a successor task to start after its predecessor finishes in Microsoft Project.

Make a Successor Task Start After Its Predecessor in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Two tasks are linked, but the successor's scheduled start date does not appear to follow the predecessor's finish date.
Observed behavior
Unexpected dates may occur because of the dependency settings, scheduling mode, constraints, calendars, actual dates, or other task settings.
Before you start

Open the project in Gantt Chart view and identify the predecessor and successor tasks. Check whether either task has already started, because actual dates can affect the schedule.

Solution 1Recommended

Check the finish-to-start link and automatic scheduling

Use this approach when a successor appears to start before its predecessor finishes.

1
Verify the dependency

Double-click the successor task, open the Predecessors tab, and confirm that the correct predecessor is listed with Type set to Finish-to-Start (FS). Set Lag to 0 if no overlap or delay is intended.

2
Enable automatic scheduling

Select both tasks in Gantt Chart view, then choose Task > Auto Schedule. Check the Task Mode column to confirm that neither task is manually scheduled.

3
Review task constraints

Double-click each task and open the Advanced tab in Task Information. Review the constraint type and date; for a project scheduled from its start date, use As Soon As Possible if a fixed constraint is not required.

4
Check actual dates and other predecessors

Open Task Information and review the successor's Predecessors tab for additional links. In the task table, insert the Actual Start and Actual Finish columns to check whether recorded progress is affecting the dates.

5
Inspect calendars and leveling

Use Project > Change Working Time to review working time, and check task or resource calendars in their respective information dialogs. Open the Resource tab's leveling options to review whether leveling has delayed the successor.

Check the finish-to-start link and automatic scheduling
A later start can be valid: A finish-to-start link prevents an automatically scheduled successor from starting before its predecessor finishes when there is no negative lag. Calendars, other predecessors, constraints, or leveling can make it start later; dates shown without times can also make tasks appear to overlap.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheets

WPS Office is a free, lightweight, easy-to-use alternative for maintaining task lists and sharing project data in familiar spreadsheet formats. Its familiar interface makes it easy to move spreadsheet-based workflows, though it does not fix Microsoft Project scheduling or replace its dependency engine.

Track predecessor and successor tasks in a spreadsheetOpen and edit Microsoft Excel XLSX files for easier sharingUse a familiar interface for spreadsheet-based workflowsWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does my successor start before its predecessor finishes?

Open the successor's Task Information > Predecessors tab and check that the link is Finish-to-Start with no negative lag. Also check the Task Mode and any actual start date, since manual scheduling or recorded progress can affect the displayed schedule.

Why does the successor start later than the predecessor's finish?

Check for positive lag and additional links on Task Information > Predecessors. Nonworking time, constraints, resource leveling, or another predecessor can also delay the successor.

Can two linked tasks show the same date without overlapping?

Yes. If times are hidden, the predecessor can finish and the successor can start later on the same day. Change the date format in File > Options > General to include a time and compare the values.

Does a deadline force a task to finish on time?

No. A deadline is a target that can produce an indicator when missed; it does not directly constrain the schedule. Review it on the Advanced tab of Task Information.