Fix Microsoft Project Dates Shifting by One or Two Days
Question details
The user wants to understand and address small task date differences after moving a Microsoft Project schedule by a year.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project is moved by one year while some tasks are manually scheduled.
- Observed behavior
- Some task dates differ by one or two days from the expected dates.
Open the project in Microsoft Project and check the Task Mode column to identify manually scheduled tasks. Note the intended new project start date and any dates that must remain fixed.
Automatically Schedule Tasks Before Moving the Project
Use automatic scheduling when Project should recalculate task dates using calendars, dependencies, and constraints.
Manually scheduled tasks do not always respond to schedule changes in the same way as automatically scheduled tasks. Switching modes can change existing task dates, so review the schedule after the move.
In Gantt Chart view, select the task rows you want Project to schedule automatically.
On the Task tab, select Auto Schedule. Check the Task Mode column to confirm the selected tasks are automatically scheduled.
On the Project tab, select Move Project, enter the intended new start date, and confirm the move.
In Gantt Chart view, compare the Start and Finish columns with your expected schedule, paying particular attention to tasks with fixed dates or dependencies.

Check Calendars, Constraints, and Dependencies
Use these checks if task dates still differ after changing the scheduling mode or moving the project.
Track Project Dates in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for working with Office files. Use WPS Spreadsheets to review and share project date tables, or migrate existing Excel planning sheets. It does not replace Microsoft Project's scheduling engine or fix Project schedules.

Frequently Asked Questions
Why did a task move by a day when I moved the project by a year?
The corresponding date in the new year may fall on a nonworking day, or a calendar exception, dependency, or constraint may affect the calculation. Check Project > Change Working Time and the task's settings.
How do I tell whether a task is manually scheduled?
In Gantt Chart view, check the Task Mode column. Select a task and use Task > Auto Schedule if you want Project to calculate its dates automatically.
Will automatic scheduling keep every date on the same day next year?
No. Automatic scheduling calculates dates using working time, dependencies, constraints, and other settings. A weekend, holiday, or leap year can change the resulting calendar date.
Where can I check a task's date constraint?
Double-click the task in Gantt Chart view, then open the Advanced tab in Task Information to review its constraint type and date.