Fix Microsoft Project Date Changes After Setting 10-Hour Days
Question details
Understand why schedule dates change after switching from eight-hour to ten-hour days and check the settings that affect task dates.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A user changes the working-day setting to ten hours while maintaining an existing project schedule.
- Observed behavior
- Task and project dates shift even though task durations appear fixed.
Identify the hours-per-day setting used when the schedule was created and whether the project and resource calendars should reflect ten actual working hours. Select a task whose dates shifted so you can compare its duration, start time, calendar, and constraints.
Check Duration Conversion and Working Calendars in Microsoft Project
Use this approach to separate the hours-per-day conversion from the calendars and task settings that determine scheduled dates.
Hours per day is a conversion factor for durations entered in days; it does not by itself define working hours on the calendar. For example, entering five days corresponds to 40 hours at eight hours per day or 50 hours at ten hours per day. Existing durations may display differently when the conversion changes, and task work is not necessarily the same as duration.
Scheduled dates also depend on working calendars, resource availability, dependencies, and constraints. Changing the conversion factor alone is not necessarily the cause of a date shift.
Go to File > Options > General and choose a date format that includes the time. Check the affected task's start and finish times in the Gantt Chart.
Go to File > Options > Schedule and review Hours per day. If the schedule was created using eight hours per day, restore that value before reviewing durations; then check the affected tasks because the displayed durations may change.
Open Project > Project Information and check the project start date and time and the selected calendar. Then open Project > Change Working Time to inspect or set the actual working hours for that calendar.
Open View > Resource Sheet and inspect the Base Calendar for assigned resources. Use Project > Change Working Time to review their working times and exceptions, and adjust them only if they should work the ten-hour schedule.
In the Gantt Chart, double-click the affected task and review its Advanced tab for a task calendar and constraint. Also check its predecessors and assigned resources before entering fixed dates or changing constraints.

Track Project Dates in WPS Spreadsheets
WPS Office is a free, lightweight alternative for maintaining project trackers in a familiar spreadsheet interface. Its Microsoft Office format compatibility makes it easy to move existing spreadsheets into WPS, although it does not fix Microsoft Project scheduling or recalculate Project calendars.

Frequently Asked Questions
Does changing Hours per day change the working calendar?
No. File > Options > Schedule controls how day-based durations are converted to hours. Use Project > Change Working Time to review or change the actual working hours on a calendar.
Why did a five-day duration change after I changed Hours per day?
A duration entered as five days represents 40 hours when Hours per day is eight and 50 hours when it is ten. Existing durations can display a different number of days after the conversion setting changes, so check the stored duration and schedule settings before editing tasks.
Where can I see the task's start time?
Go to File > Options > General and select a date format that includes time. Then inspect the Start and Finish fields in the Gantt Chart.
Why do dates still shift when the project calendar looks correct?
Assigned resource calendars, task calendars, dependencies, and constraints can also affect dates. Check View > Resource Sheet, then double-click the task in the Gantt Chart and review its Advanced tab and predecessors.