Fix the Wrong Default Task Start Date in Microsoft Project

Khadija KhanKhadija Khan Nov 13, 2026 868 views

Question details

New tasks should use the intended project start date, but Microsoft Project assigns an unexpected earlier date in a file that previously worked correctly.

Product
Microsoft Project
Device & OS
not provided
Scenario
Adding new tasks to an existing project schedule.
Observed behavior
The task start date jumps back about two months to a date used previously rather than matching the intended project start date.
Before you start

Open the affected project and note its Start date under Project > Project Information. Check whether the project is scheduled from its start date or finish date, since this affects scheduling behavior.

Solution 1Recommended

Find and correct the task with an unexpected earlier start date

Use this approach when new tasks revert to an older date and an existing task may be influencing the schedule.

In the reported case, one task had a February 1 start date. Correcting that task to a later date restored the expected start date for newly created tasks. Check for a similar outlier in your file rather than assuming every earlier date is incorrect.

1
Confirm the project start date

Select Project > Project Information and record the Start date. Confirm that it is the intended date before changing individual tasks.

2
Display the Project Summary Task

Open View > Gantt Chart. On the Format tab, select Project Summary Task in the Show/Hide group. Compare the Start field for the summary row, ID 0, with the date in Project Information.

3
Locate unusual task dates

Review the Start column for tasks beginning before the intended project start date, especially tasks using the old date that appears on newly added tasks. Right-click a column heading, select Insert Column, and choose Actual Start to check whether those tasks have recorded actual start dates.

4
Correct the affected task

Select the task with the incorrect date and correct its Start field. If Actual Start contains an erroneous date, correct that value as well. If the date remains unexpected, double-click the task and review its Predecessors and Advanced tabs for dependencies or date constraints.

5
Test a newly created task

Click an empty row in the Task Name column and enter a temporary task name. Check its Start field against the intended project start date, then delete the test task after confirming the result.

Find and correct the task with an unexpected earlier start date
Preserve valid scheduling and progress data: Do not change a legitimate earlier start date or remove an accurate Actual Start value just to make dates match. Dependencies, constraints, actual progress, and scheduling mode can legitimately place a task on a different date.
Free Microsoft Office alternative

Track Project Dates in a WPS Spreadsheet

WPS Office is a free, lightweight alternative for everyday Office work, with a familiar interface and Microsoft Office format compatibility for easy migration. Use WPS Spreadsheet to review task dates exported from Microsoft Project; it does not repair Project scheduling behavior or replace its scheduling engine.

Review exported task names, planned start dates, and actual start dates in a spreadsheet.Work with Microsoft Excel .xlsx and .xls files, including task lists exported to Excel.Use familiar spreadsheet sorting and filtering tools to identify unusually early dates.Move everyday document and spreadsheet work to a free, lightweight Office suite.
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see the Project Summary Task start date?

Open View > Gantt Chart, then select Format > Project Summary Task in the Show/Hide group. The summary task appears as ID 0; read its Start field and compare it with Project > Project Information.

Can one older task date affect the date assigned to new tasks?

In the reported case, a task starting on February 1 was associated with the unexpected default date. Correcting that task restored the expected behavior. Review tasks with unusually early Start or Actual Start values and test a new task after correcting any confirmed error.

Should I clear Actual Start to fix the date?

Only correct Actual Start if it is inaccurate. Right-click a task-table column heading, select Insert Column, and choose Actual Start to inspect it. A valid Actual Start records real progress and should not be cleared simply to align the schedule.

Why does a task still start on a different date after I correct the old date?

Double-click the task and check its Predecessors and Advanced tabs for dependencies and constraints. Also check Project > Project Information for the scheduling direction. These settings can legitimately produce a start date different from the project start date.

Can WPS Office fix the scheduling settings in my Microsoft Project file?

No. Make scheduling corrections in Microsoft Project. For a separate date review, use Project's File > Save As export options to create an Excel task list, then open that spreadsheet in WPS Spreadsheet.