Fix Unexpected Date Gaps in Microsoft Project Linked Tasks
Question details
The user needs to eliminate unexplainable date gaps of several weeks appearing between automatically scheduled linked tasks.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Scheduling a project using an 'As Late As Possible' constraint alongside a 7-day, 24-hour project calendar.
- Observed behavior
- Linked tasks do not schedule consecutively; instead, they show unexpected gaps of several weeks.
Before modifying your task constraints, review your project dependencies and check if there are any hard deadlines, as changing the constraint type will shift your scheduled dates.
Change the Task Constraint to As Soon As Possible
Switching away from the 'As Late As Possible' constraint restores normal critical path scheduling and eliminates artificial delays between linked tasks.
Microsoft Project is primarily designed to use critical path scheduling with 'As Soon As Possible' constraints. Using 'As Late As Possible' consumes both the task's total float and the float of successor tasks. Mixing these constraint types frequently causes calculation confusion and unexpected scheduling gaps.
Double-click the affected task in your Gantt chart view to open the Task Information dialog box.
Click on the 'Advanced' tab at the top of the dialog box to access scheduling settings.
Locate the 'Constraint type' dropdown menu and change the selection from 'As Late As Possible' to 'As Soon As Possible'.
Click 'OK' to save the changes. The task should now automatically snap to the earliest possible date, removing the unwanted gap.

Verify Project Start, Finish, and Calendar Settings
Ensuring the overall project information aligns with your desired calendar prevents background scheduling conflicts.
Manage Your Projects Efficiently with WPS Office
While Microsoft Project is a dedicated tool, it can sometimes be overly complex with strict constraint rules that cause unexpected scheduling behaviors. If you need a straightforward, flexible, and free way to manage project timelines, Gantt charts, and task lists, try WPS Office. It provides powerful spreadsheet capabilities that allow you to track project progress without the steep learning curve.

Frequently Asked Questions
What does the 'As Late As Possible' constraint do in Microsoft Project?
This constraint forces a task to schedule as late as it possibly can without delaying subsequent linked tasks or the overall project finish date. It consumes all available float, which often pushes tasks back and creates visual gaps in the schedule.
Why do my automatically scheduled tasks have gaps between them?
Gaps typically occur due to conflicting task constraints, resource leveling delays, manual date overrides, or mismatched project calendars that apply non-working time between the completion of one task and the start of another.
Can I use both 'As Soon As Possible' and 'As Late As Possible' in the same project?
While Microsoft Project technically allows mixing these constraints, it is generally not recommended. Mixing them frequently causes scheduling logic confusion, unexpected date gaps, and unpredictable critical path behavior.
How do I apply a 24-hour calendar to specific linked tasks only?
Double-click the task to open Task Information, go to the Advanced tab, and select your 24-hour calendar from the 'Calendar' dropdown. Check the box for 'Scheduling ignores resource calendars' if you want the task to run continuously regardless of assigned personnel.