Why a Finish-to-Start Task Starts the Same Day in Microsoft Project
Question details
Understand why a successor task starts on the same date its predecessor finishes when the finish-to-start lag is zero.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A successor task is linked to a predecessor with a finish-to-start dependency and zero lag.
- Observed behavior
- The successor starts on the same calendar day that the predecessor finishes, rather than on the following day.
Open the project and identify the predecessor and successor tasks. Check that the successor is linked with a finish-to-start dependency and that its lag is zero.
Display Task Times and Check the Working Calendar
Use this method to see whether the successor starts after the predecessor finishes but still within the same workday.
Microsoft Project schedules tasks using both dates and times. With zero lag, a successor can start later on the same day if working time remains after its predecessor finishes.
Select File > Options > General. Under Date format, choose a format that includes the time, then select OK.
In the Gantt Chart view, compare the predecessor's Finish field with the successor's Start field. The successor may begin later on the same date.
Open the successor's Task Information dialog and select the Predecessors tab. Confirm that the link type is Finish-to-Start and the lag is zero.
Select Project > Change Working Time to inspect the relevant calendar and its working hours. Also check for task or resource calendars that may affect scheduling.

Track Project Tasks in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for working with Office files. Use WPS Spreadsheets to maintain task lists and share them in Excel format. It does not fix Microsoft Project scheduling or replace its dependency engine.

Frequently Asked Questions
Does zero lag mean a successor starts the next day?
No. A finish-to-start link with zero lag allows the successor to start when the predecessor finishes, as long as applicable working time and other scheduling settings permit it.
How can I see the time for a task's start and finish?
Go to File > Options > General and choose a date format that includes time. Then inspect the Start and Finish fields in the Gantt Chart view.
Where can I check the dependency and lag?
Open the successor's Task Information dialog and select the Predecessors tab. The tab shows the link type and lag for each predecessor.
Can a calendar affect when the successor starts?
Yes. Project, task, and resource calendars can affect available working time. Select Project > Change Working Time to review calendar hours and exceptions.