Schedule a Microsoft Project Task on the First Business Day
Question details
Schedule a task for the first business day of a month after a predecessor task.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A task follows a predecessor but should start only on an eligible first business day.
- Observed behavior
- The target task should start on the first eligible business day after its predecessor permits it.
Identify the first business day of each month in your scheduling horizon, accounting for weekends and holidays. Check the working hours on those dates and decide how the predecessor should constrain the intermediate task.
Use a custom calendar and an intermediate task
Use this approach when a successor must start on an eligible first business day and you can maintain the calendar dates manually.
Create a calendar with working time only on the first business day of each month. A short, positive-duration intermediate task uses that calendar to find an eligible start date; a start-to-start link then passes its start to the target task.
Microsoft Project does not automatically identify the first business day with this setup. Extend and review the calendar exceptions as the schedule or holiday dates change.
Go to Project > Change Working Time, select Create New Calendar, and copy a calendar that reflects your normal working hours and holidays. Give the new calendar a recognizable name.
In Change Working Time, use the Exceptions tab to add nonworking date ranges between the identified first business days. For each range, use Details to set it to nonworking time. Also exclude dates before the first eligible day in your scheduling horizon.
In the task table, insert a task between the predecessor and target. Set it to Auto Scheduled and give it a short positive duration, such as 1 hour, rather than making it a milestone. Do not assign resources to this intermediate task.
Open the intermediate task's Task Information, select the Advanced tab, and choose the new calendar in the Calendar field.
Link the predecessor to the intermediate task with the relationship appropriate to your schedule, such as finish-to-start. Then link the intermediate task to the target with a start-to-start relationship. Check the resulting dates in the Gantt Chart, including months with holidays.

Track project dates in WPS Office
WPS Office is a free, lightweight alternative for maintaining project schedules in spreadsheets and sharing status documents. Its familiar interface and Microsoft Office format compatibility make it easy to move existing files, although it does not replace Microsoft Project's task-calendar scheduling.

Frequently Asked Questions
Can Microsoft Project calculate the first business day automatically with this calendar?
Not with this setup. In Project > Change Working Time, you must maintain nonworking exceptions so that only the identified first business days remain available.
Why should the intermediate task have a positive duration?
Milestones have zero duration, and Project does not reliably restrict them to their task calendars. Enter a short positive duration in the task table so the intermediate task is scheduled against the custom calendar.
Why does the target task start later than the intermediate task?
A start-to-start link does not override the target's other scheduling restrictions. Check its Task Information, resource assignments, calendar, constraints, and other predecessor links.
What happens if a holiday falls on the first weekday of the month?
Identify the next working day using your organization's holiday schedule, then set the Exceptions in Project > Change Working Time so that date remains working and the holiday is nonworking.