Schedule a Microsoft Project Task on the First Business Day

Kushani NimanthikaKushani Nimanthika Nov 22, 2026 868 views

Question details

Schedule a task for the first business day of a month after a predecessor task.

Schedule a Microsoft Project Task on the First Business Day
Product
Microsoft Project
Device & OS
not provided
Scenario
A task follows a predecessor but should start only on an eligible first business day.
Observed behavior
The target task should start on the first eligible business day after its predecessor permits it.
Before you start

Identify the first business day of each month in your scheduling horizon, accounting for weekends and holidays. Check the working hours on those dates and decide how the predecessor should constrain the intermediate task.

Solution 1Recommended

Use a custom calendar and an intermediate task

Use this approach when a successor must start on an eligible first business day and you can maintain the calendar dates manually.

Create a calendar with working time only on the first business day of each month. A short, positive-duration intermediate task uses that calendar to find an eligible start date; a start-to-start link then passes its start to the target task.

Microsoft Project does not automatically identify the first business day with this setup. Extend and review the calendar exceptions as the schedule or holiday dates change.

1
Create a task calendar

Go to Project > Change Working Time, select Create New Calendar, and copy a calendar that reflects your normal working hours and holidays. Give the new calendar a recognizable name.

2
Exclude the other dates

In Change Working Time, use the Exceptions tab to add nonworking date ranges between the identified first business days. For each range, use Details to set it to nonworking time. Also exclude dates before the first eligible day in your scheduling horizon.

3
Insert an intermediate task

In the task table, insert a task between the predecessor and target. Set it to Auto Scheduled and give it a short positive duration, such as 1 hour, rather than making it a milestone. Do not assign resources to this intermediate task.

4
Apply the calendar

Open the intermediate task's Task Information, select the Advanced tab, and choose the new calendar in the Calendar field.

5
Link and check the tasks

Link the predecessor to the intermediate task with the relationship appropriate to your schedule, such as finish-to-start. Then link the intermediate task to the target with a start-to-start relationship. Check the resulting dates in the Gantt Chart, including months with holidays.

Use a custom calendar and an intermediate task
Check the target task's constraints: The target task's own calendar, resources, constraints, and other links can move its start later than the intermediate task. If the predecessor finishes partway through an eligible day, the intermediate task may start later that day rather than at the start of business hours.
Free Microsoft Office alternative

Track project dates in WPS Office

WPS Office is a free, lightweight alternative for maintaining project schedules in spreadsheets and sharing status documents. Its familiar interface and Microsoft Office format compatibility make it easy to move existing files, although it does not replace Microsoft Project's task-calendar scheduling.

Track first-business-day dates and project milestones in a spreadsheetOpen and edit Microsoft Excel XLSX and Word DOCX filesUse a familiar interface to work with existing Office documentsWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Can Microsoft Project calculate the first business day automatically with this calendar?

Not with this setup. In Project > Change Working Time, you must maintain nonworking exceptions so that only the identified first business days remain available.

Why should the intermediate task have a positive duration?

Milestones have zero duration, and Project does not reliably restrict them to their task calendars. Enter a short positive duration in the task table so the intermediate task is scheduled against the custom calendar.

Why does the target task start later than the intermediate task?

A start-to-start link does not override the target's other scheduling restrictions. Check its Task Information, resource assignments, calendar, constraints, and other predecessor links.

What happens if a holiday falls on the first weekday of the month?

Identify the next working day using your organization's holiday schedule, then set the Exceptions in Project > Change Working Time so that date remains working and the holiday is nonworking.