Schedule a Fixed-Duration Task with Estimated Work in Microsoft Project

Maira MehtabMaira Mehtab Nov 20, 2026 870 views

Question details

Schedule a 90-day task in Microsoft Project while assigning only 60 hours of resource work.

Schedule a Fixed-Duration Task with Estimated Work in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A task spans 90 days, but its assigned resource is expected to work on it for only 60 hours.
Observed behavior
The desired schedule retains the 90-day duration and distributes the 60 hours of work across the task.
Before you start

Make sure the task and the resource you want to assign are available in your project. Check the project and resource calendars, because Project normally interprets a duration entered in days as working days.

Solution 1Recommended

Set the task to Fixed Duration and enter the resource work

Use Fixed Duration to keep the task at 90 days while specifying 60 hours of work for the assigned resource.

Fixed Duration keeps the task duration unchanged when you adjust work, while Project can recalculate the resource's assignment units. The resulting dates and distribution depend on the applicable calendars and scheduling settings.

1
Open task information

In Gantt Chart view, double-click the task to open the Task Information dialog.

2
Set the task type

On the Advanced tab, set Task Type to Fixed Duration, then click OK.

3
Enter the duration

In the task's Duration field, enter 90d. Project normally treats this as 90 working days, not 90 consecutive calendar days.

4
Assign the resource and work

On the View tab, turn on Details and select Task Form. Select the task, choose the resource in the form, enter 60h in its Work field, and click OK.

5
Review the distribution

Open View > Task Usage to check the assignment's total work and its distribution over time. Edit the time-phased work values if you need a different distribution.

Set the task to Fixed Duration and enter the resource work
Check the assignment units: Project may adjust the resource's assignment units to fit 60 hours into the fixed duration. Review the assignment and calendar if the distribution is not what you expect.
Free Microsoft Office alternative

Track task estimates in WPS Spreadsheets

WPS Office is a free, lightweight alternative for everyday Office documents. Its familiar interface and Microsoft Office format compatibility make it easy to migrate spreadsheet-based task and work estimates. It does not change Microsoft Project task scheduling.

Track task durations and estimated work in a spreadsheetOpen and edit Microsoft Excel XLSX files for spreadsheet-based planningUse a familiar interface for a smoother move from Microsoft OfficeWork with a free, lightweight Office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why does a 90-day task not need 720 hours of work?

Duration is the span of working time allocated to a task, while work is the effort assigned to resources. In Task Information > Advanced, choose Fixed Duration, then enter the resource's estimated work in Task Form.

Does 90d mean 90 calendar days in Microsoft Project?

Normally, 90d represents 90 working days according to the applicable calendar. Check Project > Change Working Time and the task's scheduling settings to understand how its dates are calculated.

Where can I see how the 60 hours are spread across the task?

Go to View > Task Usage and review the resource assignment's time-phased work values. You can edit those values to fine-tune the distribution.

What happens to resource units when I change work on a Fixed Duration task?

Project can recalculate the assignment units while retaining the task duration. Check the resource assignment in Task Form or Task Usage after entering the work.