The user needs linked tasks in Microsoft Project to recalculate when a predecessor changes.

Why Linked Microsoft Project Tasks Do Not Move Automatically
Product
Microsoft Project
Device & OS
not provided
Scenario
A predecessor task changes, and its linked successor is expected to move accordingly.
Observed behavior
The successor task remains in place instead of moving automatically.
Before you start

Open the project in Gantt Chart view and identify the predecessor and successor tasks. Check that the tasks have the intended dependency, such as Finish-to-Start.

Solution 1Recommended

Enable automatic scheduling and review task constraints

Use this approach when a linked successor remains fixed after its predecessor changes.

1
Set tasks to Auto Scheduled

In Gantt Chart view, select the affected tasks, then choose Task > Auto Schedule.

2
Show constraint information

Right-click a column heading, select Insert Column, and add Constraint Type. Add Constraint Date as well if you need to see the associated date.

3
Review unnecessary constraints

For an affected task, open Task Information > Advanced and review its constraint. If the constraint is not required, choose As Soon As Possible for a project scheduled from its start date.

4
Check the task link

Open Task Information > Predecessors and verify the predecessor, link type, and any lead or lag. For a standard dependency, use Finish-to-Start with the intended lag.

5
Test the schedule

Change the predecessor's duration or timing and check whether the successor recalculates in Gantt Chart view.

Enable automatic scheduling and review task constraints
Manually entered dates can add constraints: Entering a start or finish date can create a constraint, such as Start No Earlier Than, that prevents a task from moving as expected. Keep constraints that represent genuine scheduling requirements.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheets

WPS Office is a free, lightweight, easy-to-use alternative for everyday documents, spreadsheets, and presentations. Its familiar interface and Microsoft Office format support make it easier to move existing files, although it does not fix Microsoft Project scheduling or replace its dependency engine.

Track task names, dates, and progress in a spreadsheet.Open and edit Microsoft Office formats, including XLSX, DOCX, and PPTX.Use a familiar interface for a smoother transition from Microsoft Office.Work with a lightweight office suite for everyday files.
microsoft office alternative - wps office

Frequently Asked Questions

Why won't my successor task move earlier when I shorten its predecessor?

A constraint such as Start No Earlier Than may prevent the successor from moving earlier. Insert the Constraint Type and Constraint Date columns in Gantt Chart view, then review the constraint in Task Information > Advanced.

How do I tell whether a task is manually scheduled?

In Gantt Chart view, check the Task Mode column. Select the affected task and choose Task > Auto Schedule if you want Project to calculate its dates.

Does an actual start date stop a linked task from moving?

An Actual Start records when the task began, so Project does not move that recorded start as if it were a future planned date. Insert the Actual Start column to check it, and change it only if the recorded progress is incorrect.

Where can I check the dependency between two tasks?

Open the successor's Task Information dialog and select the Predecessors tab. Check the predecessor task, dependency type, and any lead or lag.