Fix Task Dates That Do Not Recalculate in Microsoft Project 2010

Muhammad TalhaMuhammad Talha Nov 27, 2026 868 views

Question details

The user needs partially completed tasks and their successors to reflect the correct dates in Microsoft Project 2010.

Fix Task Dates That Do Not Recalculate in Microsoft Project 2010
Product
Microsoft Project 2010
Device & OS
not provided
Scenario
A project manager marks tasks partially complete and expects unfinished work and successor dates to be rescheduled.
Observed behavior
Entering a percentage complete does not necessarily move unfinished work or recalculate successor dates as expected.
Before you start

Identify the affected tasks and the date through which progress has been reported. Check whether the status date falls before or after the tasks' actual and scheduled dates.

Solution 1Recommended

Check the Status Date and Reschedule Unfinished Work

Use this approach when partially completed tasks still have unfinished work scheduled before the reporting date.

Entering percent complete records progress, but it does not necessarily move unfinished work. The status date should reflect the reporting cutoff, with actual progress and remaining work consistent with that date.

1
Set the status date

On the Project tab, select Status Date and enter the date through which progress has been reported.

2
Review tracking fields

On the View tab, open Tables and select Tracking. Review actual start, actual duration, remaining duration, and finish dates for the affected tasks; insert any missing columns if needed.

3
Correct task progress

In the Tracking table, correct any inaccurate actual dates or remaining duration. Only change values that do not reflect the work completed or still required.

4
Reschedule unfinished work

Select the affected tasks, then choose Project > Update Project. Select Reschedule uncompleted work to start after, enter the reporting date, choose Selected tasks, and confirm.

5
Check successor dates

Return to the Gantt Chart and review the affected tasks and their successors. Check task dependencies, constraints, and calendars if dates do not move as expected.

Check the Status Date and Reschedule Unfinished Work
Check the reporting date first: If the status date is in April and the tasks are scheduled for October, moving incomplete work after the April date will not necessarily change those future tasks. Confirm the reporting date and actual progress before rescheduling.
Free Microsoft Office alternative

Track Project Task Lists in WPS Office

WPS Office is a free, lightweight alternative with a familiar interface for maintaining task lists and sharing Office documents. Open compatible files to continue working without a complicated migration; Microsoft Project scheduling issues must still be resolved in Project.

Track task names, dates, and progress in WPS SpreadsheetsWork with Microsoft Excel XLSX and XLS filesOpen and edit compatible Word DOCX and PowerPoint PPTX filesUse a familiar interface to move existing Office documents into WPS
microsoft office alternative - wps office

Frequently Asked Questions

Why does entering percent complete not move the task's finish date?

Percent complete records progress but does not automatically move all unfinished work beyond the status date. Review remaining duration in View > Tables > Tracking, then use Project > Update Project if unfinished work needs to be rescheduled.

Do I have to enter remaining duration for more than 200 tasks?

Not necessarily. Review the remaining-duration values already calculated from task progress and correct only inaccurate entries. You can select multiple affected tasks and use Project > Update Project to reschedule their unfinished work together.

What if my status date is months before the scheduled tasks?

Check Project > Status Date and confirm the intended reporting cutoff. If tasks are scheduled after that date, rescheduling unfinished work to start after it may not change their dates.

Why did a successor task stay on the same date after recalculation?

Check that the successor is linked to its predecessor and is auto-scheduled. Constraints, calendars, and other dependencies can also determine its start date; review them in the Gantt Chart and task information.

Can WPS Office fix a Microsoft Project schedule?

No. Resolve scheduling, dependencies, and recalculation in Microsoft Project. WPS Spreadsheets can maintain a separate task list in an Excel-compatible format, but it does not replace Microsoft Project scheduling.