Compare Baseline and Current Task Dates in Microsoft Project 2010

Chanuka GeekiyanageChanuka Geekiyanage Nov 27, 2026 869 views

Question details

Compare saved baseline start and finish dates with current task dates in Microsoft Project 2010.

Compare Baseline and Current Task Dates in Microsoft Project 2010
Product
Microsoft Project 2010
Device & OS
not provided
Scenario
Review schedule changes when a standard report does not directly show baseline and current task dates together.
Observed behavior
A view displays baseline and current dates side by side, with optional start and finish variances.
Before you start

Open the project and check whether a baseline has already been saved. If Baseline Start and Baseline Finish are blank, set an initial baseline before comparing dates; do not overwrite an existing baseline you need to keep.

Solution 1Recommended

Add baseline and variance columns to a custom Tracking Gantt view

Use Tracking Gantt to compare task dates side by side and save the layout for reuse in the project.

1
Open the view list

On the View tab, open Other Views and select More Views.

2
Copy Tracking Gantt

Select Tracking Gantt, click Copy, give the new view a descriptive name, and apply it.

3
Add baseline dates

In the task table, right-click a column heading and select Insert Column. Add Baseline Start and Baseline Finish, and ensure the Start and Finish columns are also visible.

4
Add variances

Use Insert Column again to add Start Variance and Finish Variance if you want to see the amount of schedule change.

5
Save the project

Select File > Save. Reopen the named view from the view list when you need the comparison again.

Add baseline and variance columns to a custom Tracking Gantt view
Baseline required: If no baseline exists, select Project > Set Baseline > Set Baseline and choose Entire project. Setting a baseline over an existing one replaces the saved comparison dates.
Free Microsoft Office alternative

Review exported project dates in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface and Microsoft Office format compatibility. Export project data to an Excel workbook to review baseline and current dates in WPS Spreadsheets; it does not replace Microsoft Project's Tracking Gantt view.

Compare exported baseline and current task dates in a spreadsheetOpen and edit Microsoft Excel XLSX files for easier migrationUse a familiar spreadsheet interface for sorting and reviewing tasksWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see baseline dates in Microsoft Project 2010?

Open Tracking Gantt from the View tab, right-click a task-table column heading, and select Insert Column. Add Baseline Start and Baseline Finish.

Why are my baseline date columns blank?

A baseline may not have been saved. To set an initial baseline, select Project > Set Baseline > Set Baseline, then choose Entire project. Avoid replacing an existing baseline you need to preserve.

How can I see how much a task has slipped?

Add the Start Variance and Finish Variance columns using Insert Column in the task table. These fields show the difference between the current and baseline schedule.

Can I reuse the comparison layout?

Yes. In View > Other Views > More Views, copy Tracking Gantt and name the new view before adding your columns. Save the project and select that view again when needed.