Display an Interim Plan in a Microsoft Project Gantt Chart

Camila MilosovichCamila Milosovich Nov 27, 2026 869 views

Question details

Display interim plan dates as bars in a Microsoft Project Gantt chart.

Display an Interim Plan in a Microsoft Project Gantt Chart
Product
Microsoft Project
Device & OS
not provided
Scenario
The user wants to compare an interim plan with the current project schedule in a Gantt or bar chart.
Observed behavior
The desired chart shows either a numbered baseline or custom Start1 and Finish1 dates alongside the current schedule.
Before you start

Check whether the dates you want to display are saved in a numbered baseline or in custom fields such as Start1 and Finish1. If you plan to save a new baseline, confirm that the current schedule contains the dates you want to capture.

Solution 1Recommended

Display a Numbered Baseline in Tracking Gantt

Use this method when the plan is saved as a numbered baseline, or when the current schedule is ready to be saved as one.

1
Save the baseline if needed

To capture the current schedule, select Project > Set Baseline > Set Baseline. Choose Set baseline, select an available numbered baseline such as Baseline 1, choose the task scope, and click OK.

2
Open Tracking Gantt

Select View > Tracking Gantt to display the tracking chart.

3
Choose the baseline

On the Gantt Chart Tools Format tab, open the Baseline menu and select the numbered baseline you want to display.

Display a Numbered Baseline in Tracking Gantt
Saving captures the current schedule: Saving a baseline captures the current schedule; it does not automatically transfer dates already stored in Start1 and Finish1. Use a custom bar style to display those fields.
Free Microsoft Office alternative

Use WPS Office to Share Project Schedule Data

WPS Office is a free, lightweight alternative with a familiar interface for working with Microsoft Office files. Use WPS Spreadsheets to review schedule data shared as an Excel file and ease migration between office suites. It does not configure Microsoft Project Gantt bars.

Review and share project schedule data in a spreadsheetOpen and edit Microsoft Excel XLSX filesWork in a familiar, easy-to-use office interfaceUse a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Where do I select the baseline shown in Tracking Gantt?

Open View > Tracking Gantt, then use the Baseline menu on the Gantt Chart Tools Format tab to select the numbered baseline.

Does saving Baseline 1 copy my Start1 and Finish1 dates?

No. Project saves the current schedule as the baseline. To display dates already stored in Start1 and Finish1, create a custom bar through Format > Bar Styles.

Why is my Start1 and Finish1 bar not showing?

In Format > Bar Styles, check that the bar's From field is Start1, its To field is Finish1, and its Show For setting matches the tasks. Also check that both date fields contain dates for those tasks.

Can a numbered baseline store more than start and finish dates?

Yes. A baseline can also capture schedule information such as work, duration, and cost. Save it through Project > Set Baseline > Set Baseline.