Display an Interim Plan in a Microsoft Project Gantt Chart
Question details
Display interim plan dates as bars in a Microsoft Project Gantt chart.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- The user wants to compare an interim plan with the current project schedule in a Gantt or bar chart.
- Observed behavior
- The desired chart shows either a numbered baseline or custom Start1 and Finish1 dates alongside the current schedule.
Check whether the dates you want to display are saved in a numbered baseline or in custom fields such as Start1 and Finish1. If you plan to save a new baseline, confirm that the current schedule contains the dates you want to capture.
Display a Numbered Baseline in Tracking Gantt
Use this method when the plan is saved as a numbered baseline, or when the current schedule is ready to be saved as one.
To capture the current schedule, select Project > Set Baseline > Set Baseline. Choose Set baseline, select an available numbered baseline such as Baseline 1, choose the task scope, and click OK.
Select View > Tracking Gantt to display the tracking chart.
On the Gantt Chart Tools Format tab, open the Baseline menu and select the numbered baseline you want to display.

Create a Gantt Bar for Start1 and Finish1
Use a custom bar style when the interim plan dates are stored in Start1 and Finish1.
Use WPS Office to Share Project Schedule Data
WPS Office is a free, lightweight alternative with a familiar interface for working with Microsoft Office files. Use WPS Spreadsheets to review schedule data shared as an Excel file and ease migration between office suites. It does not configure Microsoft Project Gantt bars.

Frequently Asked Questions
Where do I select the baseline shown in Tracking Gantt?
Open View > Tracking Gantt, then use the Baseline menu on the Gantt Chart Tools Format tab to select the numbered baseline.
Does saving Baseline 1 copy my Start1 and Finish1 dates?
No. Project saves the current schedule as the baseline. To display dates already stored in Start1 and Finish1, create a custom bar through Format > Bar Styles.
Why is my Start1 and Finish1 bar not showing?
In Format > Bar Styles, check that the bar's From field is Start1, its To field is Finish1, and its Show For setting matches the tasks. Also check that both date fields contain dates for those tasks.
Can a numbered baseline store more than start and finish dates?
Yes. A baseline can also capture schedule information such as work, duration, and cost. Save it through Project > Set Baseline > Set Baseline.