Others

Show Percent Complete as an Embedded Bar in Microsoft Project

Natalie TaylorNatalie Taylor Nov 13, 2026 869 views

Question details

The user wants to show percent complete as an embedded black progress bar with task and baseline bands in the Tracking Gantt view instead of the default dark red section.

Show Percent Complete as an Embedded Bar in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
The user is formatting the Tracking Gantt view in Microsoft Project so each task displays current dates, percent complete, and baseline information as separate bands.
Observed behavior
The current Tracking Gantt view shows percent complete as a dark red section, and some bars display only two bands rather than the desired three-band layout.
Before you start

Open the Microsoft Project file that already has the desired bar appearance, switch it to Tracking Gantt view, and keep the target project open so you can copy and compare the Bar Styles settings.

Solution 1Recommended

Copy Bar Styles settings from a project with the desired Gantt bars

Use this when you have access to a Microsoft Project file that already displays the embedded black progress bar, task band, and baseline band correctly.

1
Open the source project in Tracking Gantt view

In Microsoft Project, open the file whose bars already look correct, then go to View > Tracking Gantt.

2
Open Bar Styles

Click the Format tab, then click Format > Bar Styles. You can also right-click the Gantt chart area and choose Bar Styles.

3
Note the five bar style definitions

Record the Shape, Pattern, and Color settings for Task, Task Progress, Critical, Critical Progress, and Baseline bars.

4
Apply the same settings to the target project

Open the target project, switch to Tracking Gantt view, open Bar Styles, and set the same Shape, Pattern, and Color values for the same five bar types.

5
Keep the bar-style order identical

Preserve the order of the bar styles because styles lower in the list can override or hide styles above them.

Copy Bar Styles settings from a project with the desired Gantt bars
Bar styles applied: The Tracking Gantt bars should now show the embedded black progress section with task and baseline bands.
Free Microsoft Office alternative

Use WPS Office as a Free, Lightweight Alternative for Everyday Project Tracking

WPS Office does not modify Microsoft Project's Gantt bar styles or open .mpp project files natively, but it provides a free, lightweight office suite with familiar formatting tools. You can open and save Microsoft Word, Excel, and PowerPoint files, and build simple project progress trackers in WPS Spreadsheet.

  1. 1. Download WPS Office: Click Download WPS Office Free and install the suite on your Windows, macOS, Linux, Android, or iOS device.
  2. 2. Open existing office files: Launch WPS Office and use Writer, Spreadsheet, or Presentation to open Word, Excel, or PowerPoint files from your computer or cloud drive.
  3. 3. Create a simple project tracker: In WPS Spreadsheet, enter task names, dates, and percent complete, then use bar charts or conditional formatting to build a lightweight progress view.
Free download with no subscription for essential office toolsOpens and saves Microsoft Word, Excel, and PowerPoint file formatsFamiliar ribbon-style interface for an easier switch from Microsoft OfficeCreate simple project trackers and chart-based progress visuals in WPS SpreadsheetLightweight installation with fast startup and cross-platform support
microsoft office alternative - wps office

Frequently Asked Questions

How do I open Bar Styles in Microsoft Project?

In Tracking Gantt view, click the Format tab and then click Format > Bar Styles. You can also right-click the Gantt chart area and choose Bar Styles.

Why does my Tracking Gantt bar show only two bands instead of three?

The baseline band may be missing, hidden by another bar style, or the Gantt row may be too short. Check that the Baseline style is present, visible, and in the same order as the source project, then increase the row height if needed.

Can I change the percent complete section to black in Microsoft Project?

Yes. Open Bar Styles, select Task Progress or Critical Progress, and set Color to black. Adjust the Shape and Pattern settings to create a solid embedded progress block.

Do Bar Styles changes apply to all Microsoft Project views?

No. Bar Styles changes apply to the current Gantt-style view. Other views, such as the default Gantt Chart or Tracking Gantt, have separate bar style lists.

Does WPS Office open Microsoft Project .mpp files?

WPS Office does not natively open or edit Microsoft Project .mpp files. You can use WPS Spreadsheet to maintain a lightweight task and progress tracker with charts and conditional formatting.