Show Task Names Next to Gantt Bars in Microsoft Project 2010

Muhammad TalhaMuhammad Talha Nov 25, 2026 869 views

Question details

Show task names beside all applicable Gantt chart bars in Microsoft Project 2010.

Show Task Names Next to Gantt Bars in Microsoft Project 2010
Product
Microsoft Project 2010
Device & OS
not provided
Scenario
The user has changed Gantt chart bar style settings and wants task names to appear beside the bars.
Observed behavior
Task names do not appear beside the Gantt chart bars after the bar style settings are changed.
Before you start

Open the affected project in Gantt Chart view and identify which task bars are missing names. Note whether they are regular tasks, summary tasks, or milestones, since they may use different bar styles.

Solution 1Recommended

Check Gantt bar text and overlapping bar styles

Use this method when task names are missing after editing a bar style.

Project evaluates bar styles from top to bottom. A later style with overlapping Show For Tasks conditions may override the appearance or text settings of an earlier style.

1
Open Bar Styles

In Gantt Chart view, select Format > Bar Styles.

2
Set the task name text

Select a relevant bar style, open the Text tab, and set the Right field to Name. Repeat for other applicable styles, such as summary tasks or milestones.

3
Review later styles

In the Bar Styles list, check the Show For Tasks conditions for styles below the one you edited. If a later style matches the same tasks, adjust its conditions or set its Right text field to Name as well.

4
Apply and inspect the chart

Select OK and check the affected bars in Gantt Chart view. Reopen Format > Bar Styles if any task types still lack names.

Check Gantt bar text and overlapping bar styles
Free Microsoft Office alternative

Use WPS Office to Organize Project Task Lists

WPS Office is a free, lightweight, easy-to-use alternative for organizing task lists and related documents. Its familiar interface and Microsoft Office format compatibility make it easier to move existing documents and spreadsheets into WPS. It does not fix Microsoft Project bar styles.

Organize project task names and status information in WPS SpreadsheetsOpen and edit Microsoft Office formats such as XLSX and DOCXWork in a familiar interface that makes migration easierUse a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Where do I add task names to Gantt bars in Project 2010?

In Gantt Chart view, select Format > Bar Styles. Select a bar style, open the Text tab, and set the Right field to Name.

Why do names appear on some bars but not others?

Different task types can use different bar styles. In Format > Bar Styles, check the Show For Tasks conditions and set the text field for each applicable style.

Can another bar style override the one I changed?

Yes. Project evaluates styles from top to bottom, and a later style with overlapping Show For Tasks conditions may override an earlier one. Review the later styles in Format > Bar Styles.

How can I tell whether the problem is specific to my project file?

Create a blank project with one task and one resource, then set the relevant bar style's Right text field to Name. If the name appears there, compare its bar styles with those in the affected file.