Fix Missing Task Bars in Microsoft Project 2010 Tracking Gantt View

Emma BrownEmma Brown Nov 27, 2026 868 views

Question details

Find out why task bars are missing from the Tracking Gantt view despite valid task dates.

Fix Missing Task Bars in Microsoft Project 2010 Tracking Gantt View
Product
Microsoft Project 2010
Device & OS
not provided
Scenario
A user wants to view scheduled tasks in Tracking Gantt and compare their progress with the plan.
Observed behavior
Some task bars do not appear in Tracking Gantt, although their Start and Finish dates are valid and the tasks appear in the regular Gantt view.
Before you start

Open the project and identify an affected task by its name and Start and Finish dates. Switch between Gantt Chart and Tracking Gantt to confirm that the task is present in both views.

Solution 1Recommended

Check Tracking Gantt bar styles and critical task formatting

Use this when tasks are listed in Tracking Gantt but their bars are difficult to see or missing.

Tracking Gantt can use different bar styles for critical and noncritical tasks. Enabling critical task highlighting changes their formatting; it does not by itself guarantee that every missing bar will appear.

1
Open Tracking Gantt

On the View tab, open the Gantt Chart menu and select Tracking Gantt.

2
Check critical task highlighting

Open the Format tab and select Critical Tasks if it is not already selected. Check whether the affected bars become visible or change appearance.

3
Review bar styles

On the Format tab, open Bar Styles. Review the styles and colors for critical and noncritical task bars, including their Show For Tasks conditions and start and finish fields.

4
Make bars distinguishable

In the Bar Styles dialog, adjust a bar's shape or color if it blends into the chart background, then click OK and check the affected tasks again.

Check Tracking Gantt bar styles and critical task formatting
Baseline bars are separate: Tracking Gantt can show baseline bars alongside current task bars. A missing baseline bar may mean that no baseline has been saved for that task.
Free Microsoft Office alternative

Track Project Tasks in WPS Spreadsheet

WPS Office is a free, lightweight Office alternative with a familiar interface. Use WPS Spreadsheet to review and update task lists exported to Excel, making it easy to move everyday spreadsheet work between office suites. It does not repair Microsoft Project views.

Organize exported task names, dates, and progress in a spreadsheetOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface for everyday workWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why do bars appear in Gantt Chart but not Tracking Gantt?

The views can have different bar styles. In Tracking Gantt, open Format > Bar Styles and check the colors, task conditions, and date fields used for the affected bars.

What does the Critical Tasks option do?

The Critical Tasks option on the Format tab highlights critical tasks using the view's formatting. It can make those bars easier to distinguish, but it is not a universal fix for missing bars.

How can I bring a task's bar into view?

Select the task in Tracking Gantt, then choose Task > Scroll to Task. This moves the chart to the selected task's scheduled dates.

Why is a baseline bar missing?

A baseline bar requires saved baseline dates for the task. Check the task's baseline dates and, if appropriate for your project, use Project > Set Baseline to save a baseline.

Can WPS Office fix the Tracking Gantt view in Project 2010?

No. Tracking Gantt formatting must be changed in Microsoft Project. WPS Spreadsheet can instead help you work with task data exported to an Excel file.