Fix Gantt Chart Task Names Changing to Resource Names in Microsoft Project
Question details
The user wants Gantt chart bars to display task names consistently when tasks reach 100% completion.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project manager is reviewing task labels on a Gantt chart as tasks are completed.
- Observed behavior
- Gantt bars may display resource names instead of task names when tasks reach 100% completion.
Open the project in Microsoft Project and switch to the Gantt Chart view. Identify a completed task and an incomplete task so you can compare their bar labels and styles.
Set consistent task-name labels in Gantt Chart Bar Styles
Use Bar Styles to check which styles apply to completed and incomplete tasks and align their text fields.
Different bar styles can specify different text fields. A style that applies to completed tasks may therefore show resource names while another style shows task names.
In the Gantt Chart view, select Format > Bar Styles. Depending on your version, the command may appear on the Gantt Chart Format tab.
In the Bar Styles dialog, inspect the Show For Tasks column and select the styles that apply to the completed and incomplete tasks you want to format.
For each relevant style, open the Text tab and set the desired label position, such as Right, to Name for the task name. Remove or replace Resource Names where it is not wanted.
Select OK, then compare the labels beside completed and incomplete tasks in the Gantt Chart. Reopen Bar Styles if another applicable style still needs adjustment.

Use WPS Office for Project Documents and Spreadsheets
WPS Office is a free, lightweight alternative for working with project documents and spreadsheets in a familiar interface. Its Microsoft Office format compatibility helps make migration seamless, although it does not change Microsoft Project bar styles.

Frequently Asked Questions
Why does a completed Gantt bar show a resource name instead of a task name?
A bar style that applies to the completed task may have Resource Names selected on its Text tab. Open Format > Bar Styles to review the applicable styles and their text fields.
How do I show the task name beside a Gantt bar?
In Gantt Chart view, open Format > Bar Styles, select the relevant style, and choose Name for a position such as Right on the Text tab. Select OK to apply the change.
Should I format individual bars or change the bar style?
Change the bar style when you want consistent labels across matching tasks. Use individual bar formatting only when a specific task needs an exception.
Can WPS Office fix Microsoft Project bar styles?
No. Change Microsoft Project bar labels in its Gantt Chart view using Format > Bar Styles. WPS Office is an alternative for working with office documents and spreadsheets.