Update the Project Summary Task Name in Microsoft Project
Question details
The user wants the Project Summary Task name to reflect the project file name after using Save As.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project file has been saved under a new name, and the user wants the summary task to display that name.
- Observed behavior
- The Project Summary Task name may retain the previous name after Save As.
Open the renamed project in Microsoft Project and check that you are working in a task view such as Gantt Chart. Make the Project Summary Task visible so you can identify its row, which has ID 0.
Copy the Project File Name to the Summary Task
Use this method to update the summary task name manually after saving a project under a new name.
Open the project, select View > Gantt Chart, and on the Format tab select Project Summary Task. The summary row appears with ID 0.
Right-click a column heading in the task table, select Insert Column, and choose Project.
Copy the value displayed in the Project column, then paste it into the Task Name cell for the Project Summary Task in row 0.
Right-click the Project column heading and select Hide Column. Save the file and check the summary task name.

Update Microsoft Project and Reopen the File as XML
Try an XML round trip if the name still does not update or you suspect a problem with the project file.
Reset the Microsoft Project Global Template
Consider resetting the user Global template if the problem persists and you suspect template corruption.
Use WPS Office for Project Documents and Spreadsheets
WPS Office is a free, lightweight alternative for everyday documents and spreadsheets, with a familiar interface and Microsoft Office format compatibility that makes migration easier. It does not fix Microsoft Project or replace its project scheduling features.

Frequently Asked Questions
Where is the Project Summary Task in Microsoft Project?
In Gantt Chart view, select Project Summary Task on the Format tab. The summary task appears at the top of the task table with ID 0.
Why did the summary task keep its old name after Save As?
Microsoft Project may retain the existing summary task name when a file is renamed. You can insert the Project column and copy its displayed value into the Task Name cell for row 0.
Will saving as XML preserve all my project formatting?
Not necessarily. Save an XML copy through File > Save As, reopen it, and compare its schedule and formatting with the original before saving it as a new Project file.
What happens if I reset Global.MPT?
Project can create a new default user Global template when it restarts. Custom views, filters, and other settings stored in the old template may no longer be available, so move the original file rather than deleting it.
Can WPS Office fix a Microsoft Project summary task name?
No. Update the summary task in Microsoft Project. WPS Office can help with related documents and spreadsheets, but it does not replace Microsoft Project's scheduling features.