Update the Project Summary Task Name in Microsoft Project

Rana GarciaRana Garcia Nov 27, 2026 869 views

Question details

The user wants the Project Summary Task name to reflect the project file name after using Save As.

How to Update the Project Summary Task Name in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A project file has been saved under a new name, and the user wants the summary task to display that name.
Observed behavior
The Project Summary Task name may retain the previous name after Save As.
Before you start

Open the renamed project in Microsoft Project and check that you are working in a task view such as Gantt Chart. Make the Project Summary Task visible so you can identify its row, which has ID 0.

Solution 1Recommended

Copy the Project File Name to the Summary Task

Use this method to update the summary task name manually after saving a project under a new name.

1
Show the summary task

Open the project, select View > Gantt Chart, and on the Format tab select Project Summary Task. The summary row appears with ID 0.

2
Insert the Project column

Right-click a column heading in the task table, select Insert Column, and choose Project.

3
Copy the project name

Copy the value displayed in the Project column, then paste it into the Task Name cell for the Project Summary Task in row 0.

4
Remove the temporary column

Right-click the Project column heading and select Hide Column. Save the file and check the summary task name.

Copy the Project File Name to the Summary Task
After future renames: The summary task name may not change automatically when you use Save As again. Repeat the manual update if needed.
Free Microsoft Office alternative

Use WPS Office for Project Documents and Spreadsheets

WPS Office is a free, lightweight alternative for everyday documents and spreadsheets, with a familiar interface and Microsoft Office format compatibility that makes migration easier. It does not fix Microsoft Project or replace its project scheduling features.

Create project status reports and task lists in Writer and Spreadsheets.Open and edit common Microsoft Office formats, including DOCX and XLSX.Use a familiar interface for everyday document and spreadsheet work.Work with a free, lightweight office suite.
microsoft office alternative - wps office

Frequently Asked Questions

Where is the Project Summary Task in Microsoft Project?

In Gantt Chart view, select Project Summary Task on the Format tab. The summary task appears at the top of the task table with ID 0.

Why did the summary task keep its old name after Save As?

Microsoft Project may retain the existing summary task name when a file is renamed. You can insert the Project column and copy its displayed value into the Task Name cell for row 0.

Will saving as XML preserve all my project formatting?

Not necessarily. Save an XML copy through File > Save As, reopen it, and compare its schedule and formatting with the original before saving it as a new Project file.

What happens if I reset Global.MPT?

Project can create a new default user Global template when it restarts. Custom views, filters, and other settings stored in the old template may no longer be available, so move the original file rather than deleting it.

Can WPS Office fix a Microsoft Project summary task name?

No. Update the summary task in Microsoft Project. WPS Office can help with related documents and spreadsheets, but it does not replace Microsoft Project's scheduling features.