Hide Rolled-Up Milestones on a Microsoft Project Summary Task

Rana GarciaRana Garcia Nov 22, 2026 869 views

Question details

The user wants to hide rolled-up milestones from an unwanted higher-level summary task in Microsoft Project.

Hide Rolled-Up Milestones on a Microsoft Project Summary Task
Product
Microsoft Project
Device & OS
not provided
Scenario
Milestones in a project schedule are appearing at a higher outline level than intended.
Observed behavior
The milestones still appear on a Level 1 summary task after the milestone bars are disabled.
Before you start

Open the schedule in a Gantt Chart view and identify the Level 1 summary task where the unwanted milestones appear. Expand the outline if needed so you can distinguish the summary task from its milestones.

Solution 1Recommended

Clear the Rollup Option on the Summary Task

Use this approach to stop milestones from rolling up to the unwanted summary task without editing each milestone.

1
Select the summary task

In the Gantt Chart task list, select the Level 1 summary task showing the unwanted rolled-up milestones.

2
Open Task Information

Double-click the summary task to open Task Information.

3
Clear the rollup setting

In Task Information, find the Rollup option and clear it, then select OK.

4
Check the Gantt Chart

Return to the Gantt Chart and confirm that the milestones no longer appear on the unwanted summary task.

Clear the Rollup Option on the Summary Task
Change the summary task: This approach targets the unwanted summary task rather than requiring you to change each milestone individually.
Free Microsoft Office alternative

Track Milestones in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for working with Office documents. Use WPS Spreadsheets to create a simple milestone tracker and move existing Excel files into your workflow. WPS does not change Microsoft Project rollup settings.

Create a simple milestone tracker in WPS SpreadsheetsOpen and edit Microsoft Excel XLSX filesWork with Microsoft Word DOCX and PowerPoint PPTX filesUse a familiar interface for an easier transition from Microsoft Office
microsoft office alternative - wps office

Frequently Asked Questions

Why are milestones still visible after I disable their bars?

The summary task's rollup setting may still be enabled. Double-click the unwanted summary task, find the Rollup option in Task Information, and clear it.

Do I need to edit every milestone to hide the rollup?

Not for this approach. Select the unwanted Level 1 summary task and clear its Rollup option in Task Information.

Where can I check whether the milestones are still rolled up?

Return to the Gantt Chart after saving the Task Information change and inspect the bar for the affected summary task.

Can WPS Office change rollup settings in Microsoft Project?

No. Change the rollup setting in Microsoft Project. WPS Spreadsheets can instead be used to create a separate milestone tracker.