Show Selected Subproject Tasks and Milestones in Microsoft Project
Question details
Show selected tasks or milestones from subprojects in a master plan while retaining useful links to the source schedules.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A master plan needs a concise view of selected subproject work for reporting and cross-project scheduling.
- Observed behavior
- Linked subprojects can display their tasks in the master plan, but selecting only relevant items while maintaining dependencies requires careful project design. Links may also break if project files are moved or renamed.
Identify the subproject tasks that should appear in the master report and decide whether live scheduling dependencies are required. Keep linked project files in stable locations and confirm you can open each source file.
Link master-project milestones to selected subproject tasks
Use this approach when the master plan needs a small set of reporting milestones with scheduling links to subproject tasks.
A linked master milestone is a separate task, not a live copy of the subproject task. Its scheduled date depends on the link type, calendars, constraints, and scheduling settings; the link does not automatically copy task status or completion.
In Microsoft Project, open the master plan and use Project > Subproject to insert the relevant subproject if it is not already available in the plan.
In the master plan's Gantt Chart view, enter a new task for each item you want to report and set its Duration to 0 days. Use automatic scheduling if the milestone should respond to its predecessor.
Expand the inserted subproject, select the source task and then the master milestone, and choose Task > Link Tasks. Check the resulting dependency in the milestone's Task Information dialog under Predecessors.
Change a source task's scheduled date in a test and check the master milestone's resulting date. Keep linked files in their established locations and avoid renaming or moving them.
Create an unlinked consolidated plan for filtered reporting
Use a static consolidated plan when a filtered overview is more important than automatic updates from subprojects.
Prepare Project Reports with WPS Office
WPS Office is a free, lightweight, easy-to-use alternative for preparing project reports and presentations. Its familiar interface and Microsoft Office format compatibility make it easier to move existing documents into your reporting workflow. It does not replace Microsoft Project's live scheduling links.

Frequently Asked Questions
Will a linked master milestone copy the subproject task's status?
No. A dependency affects scheduling but does not automatically copy the source task's status or completion. Review the source task separately when preparing status reports.
Why does my master milestone show a different date from the source task?
The dependency type, calendars, constraints, and scheduling settings can affect the milestone date. Open the milestone's Task Information dialog and check its Predecessors tab.
How can I show only higher-level tasks in a consolidated plan?
In Gantt Chart view, use View > Outline and choose the level you want to display. This changes the visible outline, not the underlying tasks.
What should I check if external links or ghost tasks look wrong?
Confirm that the linked project files still exist at their expected locations and open them in Microsoft Project. Review dependencies in Task Information > Predecessors, especially if files were moved, renamed, or improperly unlinked.
Does an unlinked consolidated plan update when a subproject changes?
No. When Link to project is cleared in the Insert Project dialog, the inserted data is not a live link. Update or recreate the consolidated report to reflect source changes.